Planned Activity (tsspc2600m000)
Use this session to view and maintain the list of activities planned for the preventive maintenance of a installation group.
A list of planned activities can be generated for an Installation group, or a range of Installation groups, using the Generate Maintenance Plan (tsspc2200m000) session. Planned activities can also be added manually using the details session.
Planned activity linesThe lines on the tabs refer to the following sessions:
- Material Requirements: The lines on the material requirements tab refer to the Planned Activity - Material Requirements (tsspc2110m000) session. Double-click the material requirements for more detailed information.
- Labor Requirements: The lines on the labor requirements tab refer to the Planned Activity - Labor Requirements (tsspc2111m000) session. Double-click the labor requirements for more detailed information.
- Other Requirements: The lines on the other requirements tab refer to the Planned Activity - Other Requirements (tsspc2112m000) session. Double-click the other requirements for more detailed information.
- Costs Overview: The lines on the costs overview tab refer to the Planned Activity - Costs Overview (tsspc2513m000) session. Double-click the costs overview for more detailed information.
- Required Skills: The lines on the required skills tab refer to the Required Skills by Activity (tstdm2111m000) session. Double-click the required skills for more detailed information.
- Subassemblies: The lines on the subassemblies overview tab refer to the Planned Activity - Subassemblies (tsspc2150m000) session. Double-click the subassemblies overview for more detailed information.
Field Information
- Top Item
-
The item code of the highest-level serialized item in the physical-breakdown structure, to which this serialized item belongs.
Note:- The top serialized item is displayed in this field after its status is set to Active.
- Each time the physical breakdown is changed, the top serialized item is updated.
- Top Serial Number
-
The serial number of the topmost serialized item in this item's physical breakdown.
- Description
-
The description or name of the top serial number.
- Installation Group
-
The code of the installation group for which the activities are planned.
- Description
-
The description or name of the installation group.
- Item
-
The code of the item for which the activity is planned.
Note: If the Items Service by Office is Mandatory check box is selected in the General Service Parameters (tsmdm0100m000) session, you can only select an item that is linked to the specified Service Office. The service items are linked to the service office in the Items - Service by Service Office (tsmdm2120m000) session. - Serial Number
-
The serial number of the item for which the activity is planned.
- Description
-
The description or name of the serial number.
- Alternate Serial Number
-
If business partner's use their own serial numbers as an alternative to item's manufactured one, the business partner's alternative is given in this field.
Note: Alternate serial numbers are given in the Serialized Items (tscfg2100m000) session. - Location Address
-
The address and the location of the activities planned for the preventive maintenance of an installation group.
- Description
-
The description or name of the code.
-
The complete address of the location.
- Search Argument
- Planned Activity
-
The code of the planned activity.
- Line
-
The planned activity line number
- Status
-
Status of the planned activity.
- Reference Activity
-
The code of the planned activity.
- Description
-
The description or name of the planned activity.
- Service Type
-
The service type.
- Description
-
The description or name of the service type.
- Coverage Type
- Description
-
The description or name of the coverage type.
- Checklist
-
Note: The default value is that given to the activity in the Reference Activities (tsacm1101m000) details session.
- Maintenance Scenario
-
The series code of the maintenance scenario to which the planned activity is linked.
Note: When you specify a new planned activity and reference activity for a serialized item, the application considers the maintenance scenario and the reference activity to default the first maintenance scenario line that is found. - Scenario Line
-
The line number of the maintenance scenario.
- Pattern Line
-
The sequence number that allows multiple pattern lines under the same scenario line.
- Description
-
The description or name of the code.
- Origin
-
Indicates the origin of the planned activity.
Allowed values
- Manual
- Call
- Maintenance Plan
- Activity Group
- Activity Use
-
The option to define the usage of reference activity.
Allowed values
- Field Service
-
The reference activity can be used only for Field Service usage.
- Depot Repair
-
The reference activity can be used only for Depot Repair usage.
- General
-
The reference activity is not restricted to any particular usage and can be used generally. This activity can be used for Field Service and/or depot repair.
- Rental
-
The reference activity can be used only for Rental usage.
- Description
-
The description or name of the reference activity group.
- Site
-
The code of the site assigned to the planned activity.
Note: This field is displayed only if the Sites field is set to Active or In Preparation in the Implemented Software Components (tccom0100s000) session. - Downtime Ratio
- Text
- Measurement Type
-
The description or name of the measurement type.
- Activity Duration
-
The duration of the planned activity. The default value is that given to the activity in the Reference Activities (tsacm1101m000) session.
- Travel Duration
-
The time required to travel from the service department to the Installation group's Planned Activity (tsspc2600m000). The default value is that given to the Installation group in the Installation Groups (tsbsc1100m000) session.
- Planned Start Time
-
Planned start time of the activity.
- Planned Finish Time
-
Planned finish time of the activity.
- Earliest Start Time
-
The activity's earliest acceptable start time. The default value is determined by the reference activity's Reference Activities (tsacm1101m000) details session.
- Latest Finish Time
-
The activity's latest acceptable finish time. The default value is determined by the reference activity's Reference Activities (tsacm1101m000) details session.
- Appointment
-
If this check box is selected, an appointment has been arranged with the customer for the planned activity to be carried out by the service engineer.
If this check box is cleared, no appointment has been arranged.
- Operations Department
-
The service department that carries out the reference activity.
Note: The default value is that given to the activity in the Installation Groups (tsbsc1100m000) session. - Description
-
The description or name of the service department.
- Subcontractor
-
The code of the buy-from business partner who carries out any subcontracted work required by the activity.
- Name
-
The description or name of the buy-from bp.
- Item Subcontracting
-
The code of the service item or cost item required in order to complete the reference activity if a subcontractor is required.
The service/cost item is used on a purchase order line. The item is required because you cannot add an activity to a purchase order line, the item will be used as an activity definition. This item will be used as a default item when generating purchase orders.
- Description
-
The description or name of the service/cost item.
- Master Routing
-
The master routing used to generate the activity..
- Description
-
The description or name of the master routing.
- Routing Option
-
Routing Options that were used to generate the service order activity.
- Description
-
The description or name of the routing option.