Switch Status Maintenance Plan (tsspc2201m000)
Use this session to change the status of the planned activities specified for the maintenance plan. You can access this session using the Switch Status... option in the Planned Activities (tsspc2100m000) session. You can select a range of maintenance scenarios, serialized items and planned activities.
- The To-selection range values must not be lesser than the From-selection range values.
- The selection range for the Owner, In Use-by Business Partner, Installation Group, Serialized Item Group and Usage Class fields is used to set more accurate browse filters for the From Item and To Serial Number range.
- If a planned activity is transferred to a service order or a maintenance sales order and this order is not canceled, the application does not change the status of the activity but a message is printed in the error report.
- If a planned activity transferred to a service order or a maintenance sales order is canceled, the application does not change the status of the activity but a message is printed in the error report.
- You cannot change the status if only one status check box is selected in the Activity Status group box and this status is same as the value set in the Switch Status To field.
- You must select at least one check box in the Activity Use and the Activity Status group boxes.
Field Information
- Selection Range
-
Use the fields in the Selection Range group box to specify the range of data for which the status of the planned activities must be changed.
- Selection Maintenance Scenarios
-
The setting for the selection of the maintenance scenarios.
Allowed values
- All Maintenance Scenarios
- Selection of Scenarios
- Type of Scenario
-
The type of scenario for which the status is changed.
Allowed values
- Usage Based Only
- Time Based Only
- Time Based and Usage Based
- Maintenance Scenario
-
The From and To fields define a range of: the maintenance scenario codes.
- Scenario Line
-
The From and To fields define a range of: the maintenance scenario lines.
- Selection Serialized Items
-
The setting for the selection of the serialized items.
Allowed values
- All Serialized Items
- Selection of Serialized Items
- Selection of Top Items
- Owner
-
The From and To fields define a range of: the sold-to business partners specified for the serialized item.
- In Use-by Business Partner
-
The From and To fields define a range of: the in use-by business partners.
- Installation Group
-
The From and To fields define a range of: the installation groups.
- Serialized Item Group
-
The From and To fields define a range of: the serialized item groups.
- Usage Class
-
The From and To fields define a range of: the usage classes.
- From Item
-
The From and To fields define a range of: the items.
- From Serial Number
-
The From and To fields define a range of: the serial numbers.
- Selection Planned Activities
-
The setting for the selection of the planned activities.
Allowed values
- All Planned Activities
- Selection of Planned Activities
- Activity Group
-
The From and To fields define a range of: the activity groups.
- Master Routing
-
The From and To fields define a range of: the master routings.
- Reference Activity
-
The From and To fields define a range of: the reference activities.
- Planned Activity
-
The From and To fields define a range of: the planned activities.
- Service Office
-
The From and To fields define a range of: the service departments.
- Activity Line
-
The From and To fields define a range of: the activity lines.
- Planned Start Time
-
The From and To fields define a range of: the planned start time.
- Free
-
If this check box is selected, the planned activities with the status Free are included in the selection.
Note: By default, this check box is selected. - Released
-
If this check box is selected, the planned activities with the status Released are included in the selection.
- Transferred
-
If this check box is selected, the planned activities with the status Transferred are included in the selection.
- Canceled
-
If this check box is selected, the planned activities with the status Canceled are included in the selection.
- Field Service
-
If this check box is selected, the planned activities with the Activity Use field set to Field Service are included in the selection.
Note: By default, this check box is selected. - Repair Center
-
If this check box is selected, the planned activities with the Activity Use field set to Depot Repair are included in the selection.
Note: By default, this check box is selected. - General
-
If this check box is selected, the planned activities with the Activity Use field set to General are included in the selection.
Note: By default, this check box is selected. - Switch Status To
-
The status to which you want to update the selected planned activities.
Allowed values
- Released
- Transferred
- Canceled
- Free
- Check ATP Inventory
-
If this check box is selected, the ATP check is performed to determine the available inventory.
- Skip Blocked Inventory
-
If this check box is selected, the blocked quantity is subtracted from the On Hand quantity during the Planned Inventory check and the On Hand Inventory check.
Note: This field is enabled only if the Check Planned Inventory or the Check On Hand Inventory check box is selected. - Check Planned Inventory
-
If this check box is selected, the planned inventory check is performed to determine the available inventory.
- Block Releasing of Orders with Shortages
-
If this check box is selected, the orders with insufficient inventory are not processed.
Note: This field is enabled only if the Check Planned Inventory or the Check On Hand Inventory check box is selected. - Check On Hand Inventory
-
If this check box is selected, the on hand inventory check is performed to determine the available inventory.
- Scope of Inventory Check
-
The scope to check the availability of the material.
Allowed values
- All Warehouses in Planning Cluster
-
Checks if the material is available in the warehouse defined on the Material Line.
- Current Warehouse Only
-
Checks if the material is available in one of the warehouses in the same cluster as the warehouse defined on the Material Line.
Note: This field is enabled only if the Check Planned Inventory or the Check On Hand Inventory check box is selected. - Update Activities with Latest Planned Material Line
-
If this check box is selected, the material availability data of the latest planned material line is updated on the related planned activities.
- Simulate
-
If this check box is selected, actual delete actions are not executed.
- Process Report
-
If this check box is selected, all the planned activities, for which the status has been changed, are printed in a process report ordered on serialized item.
Note: By default, this check box is selected and disabled if the Simulate check box is selected. - Error Report
-