Planned Activity - Labor Requirements (tsspc2111m000)
Use this session to view and maintain the labor requirements of a planned activity.
If you manually add an activity in the Planned Activities (tsspc2100m000) session, LN asks if you want to list its labor requirements in this session.
If you delete a planned activity from the Planned Activities (tsspc2100m000) session, its labor requirements are automatically deleted from this session.
Field Information
- Planned Activity
-
The number that identifies serialized item for the planned activities.
Note: LN generates the planned activity number based on the data specified in Number Group for Planned Activities and Series for Planned Activities fields in Service Planning Parameters (tsspc0100m000) session. - Activity Line
-
The line number that distinguishes one Planned Activity from another for the same Planned Activity Number.
Note: LN generates the planned activity line number based on the data specified in Number Group for Planned Activities, Series for Planned Activities and Step Size for Activity in Service Planning Parameters (tsspc0100m000) session. - Installation Group
-
The code of the Installation group for which the activity is planned.
- Description
-
The name or description of the Installation group.
- Owner
-
The sold-to business partner or the internal department that owns the Installation group.
- Activity
-
The code of the planned activity that requires the task(s) displayed.
- Description
-
The name or description of the activity.
- Activity Status
-
The status of the activity.
- Line
-
The number used to distinguish one task from another in the list of an activity's labor requirements.
- Task
-
The code of the task required by the planned activity.
- Description
-
The name or description of the required task.
- Time Quantity
-
The amount of time required to carry out the task. This value multiplied by the labor rate determines the task's cost amount of labor.
Note: The default value is the value specified for the task in the Tasks (tsmdm0115m000) session. - Efficiency Rate
-
The number of employees required to perform the task.
- Cost Component
-
The code of the cost component used to categorize the cost of the required labor.
- Description
-
The name or description of the cost component.
- Labor Rate Code
-
The labor rate expressed in a currency.
- Labor Rate
-
The units in which the labor rate is calculated.
- Cost Amount
-
The cost amount expressed in a currency.