Time Based Scenario Line - Patterns (tsspc1631m000)

Use this session to create and maintain time based patterns based on which planned activities are generated. For a time based pattern maintenance scenario line, the maintenance plan, consisting of planned activities, is generated based on time and a predefined pattern. For example: You can perform minor maintenance after two months, extensive maintenance after three months, minor maintenance after five months and so on.

Field Information

Maintenance Scenario

The series code of the maintenance scenario.

Description

The description or name of the code.

Line

The line number of the maintenance scenario. Each line is identified with a unique number generated by LN. By default, LN increases the existing number by a predefined value. However, you can change the value.

Description

The description or name of the code.

Text

The text relevant to the time based scenario line.

Master Routing

The code of the master routing.

Routing Option

The code of the routing option.

Cyclic

If this check box is selected, planned activities are generated continuously within the specified date range.

Shift Related Planned Activities

If this check box is selected, based on the planned start or finish date LN changes the related planned activities that are planned at a later point in time.

Maintenance Cycle

The time frequency for the repetition of the maintenance plan.

Note: 
  • This field is enabled and mandatory if:
    • The Cyclic check box is selected.
    • The Type field is set to Time Based Pattern.
  • This value is defaulted from the Preventive Maintenance Scenarios (tsspc1130m000) session.
Maintenance Cycle Unit

The time unit in which the period for the maintenance cycle is expressed.

Note: 
  • This field is mandatory if the value in the Maintenance Cycle field is greater than 0.
  • This value is defaulted from the Preventive Maintenance Scenarios (tsspc1130m000) session, and you can modify this value only if the Activity Pattern field is set to Relative.
Description

The description or name of the code.

Consider Last Planned Activity Date

If this check box is selected, the last planned activity date, generated for the pattern line, is considered to start the maintenance cycle start time.

Note: 

This check box setting is defaulted based on the value you set for the Consider Last Planned Activity Date check box in the Preventive Maintenance Scenarios (tsspc1130m000) session, if:

  • The Type field is set to Time Based or Time Based Pattern.
  • The Activity Pattern field is set to Relative.
Activity Pattern

The code used to identify the pattern of your activities.

Allowed values

Absolute
Relative
Not Applicable