Preventive Maintenance Scenario Lines (tsspc1131m000)

Use this session to create and maintain preventive maintenance scenario lines based on which a maintenance plan is generated for a serialized item.

Scenarios can be:

  • Usage Based. Example execute maintenance after 10000 km or after profile of the tire is below 3 mm.
  • Time Based. Example 12 times a year.
  • Based on time according to a predefined pattern. Example perform minor maintenance after two months, extensive maintenance after three months, minor maintenance after five months.

Field Information

Maintenance Scenario

The series code of the maintenance scenario.

Description

The description or name of the code.

Line

The line number of the maintenance scenario. Each line is identified with a unique number generated by LN. By default, LN increases the existing number by a predefined value. However, you can change the value.

Description

The description or name of the code.

Type

The type of maintenance scenario line.

Allowed values

Time Based

For a time based maintenance scenario, the maintenance plan is generated either on master routing or for a reference activity.

Usage Based

For a usage based maintenance scenario, the maintenance plan is generated if the scenario line is setup for a specific child item that matches with the item of the serialized item.

Time Based Pattern

For a time based pattern maintenance scenario, the maintenance plan is generated either on master routing or for a reference activity.

Measurement Type

The code of the measurement type.

Note: Only applicable for usage based scenario lines.
Description

The description or name of the code.

Specific Position

If this check box is selected, the maintenance scenario line is specific to a position of the item.

Note: Only applicable for usage based scenario lines.
Position

The position code of the item.

Note: only applicable when specific position is selected.
Description

The description or name of the code.

Reference Activity

The reference activity from which a planned activity is generated.

Description

The description or name of the code.

Master Routing

The code of the master routing from which a planned activity is generated.

Routing Option

The code of the routing option from which a planned activity is generated.

Specific Child Item

If this check box is selected, the maintenance scenario line is applicable to the specific child item.

Child Item

The child item for which maintenance plan is generated.

During Life Cycle

If this check box is selected, planned activities are generated within the defined life cycle of the item. The life cycle can be defined in Items - Service (tsmdm2100m000) session.

Cyclic

If this check box is selected, planned activities are generated continuously within the specified date range.

Frequency

The number of times the reference activity is to be carried out.

Unit

The unit in which the frequency is expressed.

Trigger Set

The code of the maintenance trigger set.

Note: 
  • This is a display field.
  • This value is defaulted from the Usage Based Scenario Line (tsspc1131m100) session.
Description

The description or name of the code.

Maintenance Cycle

The time frequency for the repetition of the maintenance plan.

Note: 
  • This field is enabled and mandatory if:
    • The Cyclic check box is selected.
    • The Type field is set to Time Based Pattern.
  • This value is defaulted from the Preventive Maintenance Scenarios (tsspc1130m000) session.
Maintenance Cycle Unit

The time unit in which the period for the maintenance cycle is expressed.

Note: 
  • This field is mandatory if the value in the Maintenance Cycle field is greater than 0.
  • This value is defaulted from the Preventive Maintenance Scenarios (tsspc1130m000) session, and you can modify this value only if the Activity Pattern field is set to Relative.
Description

The description or name of the code.

Consider Last Planned Activity Date

If this check box is selected, the last planned activity date, generated for the pattern line, is considered to start the maintenance cycle start time.

Note: 

This check box setting is defaulted based on the value you set for the Consider Last Planned Activity Date check box in the Preventive Maintenance Scenarios (tsspc1130m000) session, if:

  • The Type field is set to Time Based or Time Based Pattern.
  • The Activity Pattern field is set to Relative.