Resource Requirements by Site (tsacm2122m000)
Use this session to maintain the resource requirement for the combination of the reference activity and the site.
Field Information
- Reference Activity
-
The reference activity for which the resource requirements are defined.
- Site
-
The code of the site to which the reference activity is linked.
- Line
-
The number that is used to identify the resource requirements for the reference activity.
- Resource Type
-
The type of resource that is required for the reference activity.
Allowed values
- Labor
-
The labor required to execute a reference activity. The required labor time can be only be specified when the reference activity is used for field service.
- Tool
-
The tool required to execute the reference activity. This tool is returned after the Reference Activity is completed.
- Subcontracting
-
The subcontracting requirement. In case the reference activity is specified for subcontracting, and it is used for field service then the subcontracting requirement must be specified.
- Other
-
The resource that is needed and which cannot be scaled, is termed as Other Resource Types.
- Material
-
Materials that are needed to execute the reference activity.
Note:- The Subcontracting option is displayed only if the Subcontracted check box is selected in the Reference Activities (tsacm1101m000) session.
- You cannot change this value if this field is set to Subcontracting and this resource requirement line is linked to a material resource requirement line.
- Related Subcontracting Line
-
The line number of the subcontracting resource requirement line to which the material resource requirement line is linked.
Note:- This field is displayed only if the Subcontracting with Material Flow check box is selected in the Implemented Software Components (tccom0100s000) session.
- This field is enabled only if:
- The Activity Use field is set to Field Service for the related Reference Activity in the Reference Activities (tsacm1101m000) session.
- The Subcontracted and the Supply Material to Subcontractor check boxes are selected for the related Reference Activity in the Reference Activities (tsacm1101m000) session.
- The Resource Type field is set to Material.
- You must specify this value if there is more than one subcontracting resource requirement line for the reference activity.
- Description
-
The description if the resource type is Other.
- Text
-
The additional information related to the resource requirement.
- Item
-
The item for Material, Tool or Other resource.
Note:- This field is enabled only if the Resource Type field is set to Material or Tool.
- This field is disabled if the Resource Type field is set to Labor.
- If the Activity Use field is set to Field Service for the related Reference Activity in the Reference Activities (tsacm1101m000) session and Resource Type field is set to Subcontracting, you can specify the item of the type, Subcontracted Service.
- You cannot specify the same Item of the type Subcontracted Service for more than one subcontracting resource requirement line because on a service order subcontracting other cost line, if the unit cost is defaulted based on the linked reference activity, LN must be able to identify the subcontracting resource requirement that must be used.
- Delivery Type
-
The method by which the required materials are delivered.
Allowed values
- From Service Kit
-
A service kit is used to solve calls with a minimum set of spare parts, or just as a standard set of basic spare parts that are frequently used. The service kit is replenished on actual usage, and is not assigned in the estimated service-order cost calculation.
- From Service Inventory
-
Bulk materials such as bolts and nuts.
- From Dealer's Inventory
- By Purchase Order
-
Parts that are not held on stock, such as expensive parts or non-storable parts, and that must be purchased. A purchase order for these parts is generated when you run global SRP.
- By Field Purchase
-
Parts that must be purchased locally at the location where the activity is carried out.
- To Scrap
- To Warehouse
-
Parts that must be returned to the warehouse, for example, insurance parts that are refurbished in an overhaul shop (not applicable to maintenance items).
- To Warehouse by Transport
-
Parts that must be returned to the warehouse, and that must be transported in a special way, for example, transport on a special truck (not applicable to maintenance items).
- Supplier Direct Delivery
- Supplier Direct Return
- Not Applicable
- From Warehouse
-
If the delivery is from a central or regional warehouse, and the warehouse on the material line is specified, the planned deliveries are normally allocated in the warehouse of the item. Use this delivery type if no service cars are defined, or if service cars are not defined as separate warehouses.
- From Warehouse in Car
-
Select this option if parts are transported by a service car and these service cars are defined as separate warehouses. During global SRP, allocations are made in the central warehouse. While Releasing a Service Order, a transfer order is created from the central warehouse to the service car.
- From Car
-
Parts are transported by a service car related to warehouse and transfer warehouse orders are not generated.
The car must be replenished using the normal warehouse procedures such as Time Phased Order Point (TPOP) or Order Controlled/Batch (OCB).
- From Warehouse by Transport
-
Select this option if parts must be separately transported because of their size. While Releasing a Service Order, a transfer order is created from the central warehouse to the warehouse that is defined for the ship-to business partner.
Note:- The From Warehouse and By Purchase Order options are displayed only if the Ownership field is set to Company Owned.
- The option From Warehouse by Transport and Supplier Direct Delivery options are displayed only if the Activity Use field is set to Field Service in the Reference Activities (tsacm1101m000) session.
- The Supplier Direct Delivery option is displayed only if the Supply Material to Subcontractor check box is not selected in the Reference Activities (tsacm1101m000) session.
- The option From Car is displayed only if Activity Use (of the linked reference activity) field is not set to Depot Repair in the Reference Activities (tsacm1101m000) session.
- The option From Warehouse in Car is displayed only if Activity Use (of the linked reference activity) field is not set to Depot Repair in the Reference Activities (tsacm1101m000) session.
- Ownership
-
The ownership of the service item. This value is defaulted from the Items - Service (tsmdm2100m000) session.
Allowed values
- Company Owned
-
company owned
- Consigned
-
consigned
- Customer Owned
-
customer owned
- Return as Issued
-
When items are returned from the production environment to the warehouse, for example, because fewer items were required than issued for production, the original owner at the time of issue will become the owner again (unless the items are damaged).
- Deferred
-
The date the ownership is transferred from supplier to customer is still unknown. The change date is determined after the items are picked, and depends on both the warehouse types involved in the goods transfer and the agreement between supplier and customer.
- Not Applicable
-
Your own organization owns the inventory. Ownership behavior refers only to not-owned inventory.
- Customer Furnished Material
-
Indicates the ownership of the material. LN selects this check box if the material is furnished by the customer.
Note:- This field is displayed only if the Customer Furnished Materials check box is selected in the Implemented Software Components (tccom0100s000) session.
- This check box is selected only if:
- The Ownership field is set to Customer Owned.
- The Delivery Type field is set to From Warehouse or To Warehouse (for unconsumed material).
- Subject to Trade Compliance
-
If this check box is selected, the trade compliance checks must be performed for the material line associated with the selected item.
Note: This field is displayed only if the Trade Management check box is selected in the Implemented Software Components (tccom0500m000) session. - Critical for Activity Release
-
If this check box is selected, the material line on which the item is used is blocked because of the trade compliance check failure. If the material line fails the compliance check, the related activity or the order cannot be released.
Note:This field is displayed only if the Trade Management check box is selected in the Implemented Software Components (tccom0500m000) session.
This value is defaulted from the Critical for Activity Release check box in the Items - Service (tsmdm2100m000) session.
This check box is applicable only for the site related item data.
This check box is applicable only for the materials.
- Material Site
-
The code of the site to which the Warehouse is linked.
- Warehouse
-
The code of the warehouse for the material line.
Note:- This field is set to Not Applicable and is disabled if the Resource Type field is set to a value other than Material.
- The specified warehouse must be of the type Normal, Service, Service Reject or Consignment (Not Owned).
- You can select the warehouse of type Consignment (Not Owned) only if the Delivery Type field is set to From Warehouse and the Ownership field is set to Company Owned.
- If the Delivery Type field is set to From Car or From Warehouse in Car:
- The warehouse must be linked to the service car defined in the Service Cars (tsmdm1145m000) session.
- the WMS Controlled check box must not be selected for the warehouse in the Warehouses (whwmd2500m000) session.
- You can specify a WMS Controlled warehouse of type Normal and Service if for the specific reference activity the Activity Use is not set to Depot Repair in the Reference Activities (tsacm1101m000) session.
- The warehouse must be linked to the logistic company.
- Ship Materials To
-
The address type used as the address to ship the items.
Note:- This field is applicable only if the Resource Type is set to Material.
- The value in this field is set to Subcontractor Address if:
- The Resource Type is set to Material and
- The Activity Use field is set to Depot Repair and Supply Material to Subcontractor check box is selected in the Reference Activities (tsacm1101m000) session.
- The value in this field is set to Location Address, Ship-to BP Address and Subcontractor Address if:
- The Resource Type is set to Material and
- The Activity Use field is set to Field Service and Supply Material to Subcontractor check box is selected in the Reference Activities (tsacm1101m000) session.
Allowed values
- Ship-to BP Address
- Location Address
- Owner Address
- In-Use-by BP Address
- Dealer Address
- Subcontractor Address
- Not Applicable
- Task
-
The task code.
Note: In case of a labor line, the Task can be specified by means of a Task definition. - Efficiency Rate
-
The number of hours required to complete the reference activity.
Note: This field is enabled only if the Resource Type field is set to Labor. - Quantity
-
The number of resources required. By default, LN sets this value as one. You can modify this value.
- Unit
-
The unit in which the quantity of the resource is expressed.
Note:- For the resource requirement of the type Material:
- This value is defaulted from the Sales Quantity Unit field in the Items - Service (tsmdm2100m000) session.
- You can select the unit from the Units by Unit Set (tcmcs0112m000) session, based on the unit set linked to the item.
- For the resource requirement of the type Other, you can select the unit from the Units (tcmcs0101m000) session.
- For the resource requirement of the type Material:
- Cost Component
-
The cost component
- Unit Cost
-
The price per unit when resource type is Other, expressed in the reference currency. Unit cost is retrieved from the Item - Costing (ticpr0107m000) session.
Note:- This value is defaulted from the Service Subcontracting Purchase Price field in the Items - Purchase (tdipu0101m000) session and cannot be modified if:
- The specified Item is of the type Subcontracted Service.
- The Source of Price for Service Subcontracting for the Item is set to Price Book / Contract in the Items - Purchase (tdipu0101m000) session.
- Else, you can specify this value.
- This value is defaulted from the Service Subcontracting Purchase Price field in the Items - Purchase (tdipu0101m000) session and cannot be modified if:
- Currency
-
The company's reference currency defined in the Companies (tcemm1170m000) session.
- Standard Cost
-
The price per unit when resource type is Material or Tool, expressed in the reference currency.
The prices per unit are displayed as follows:
- Material resource type: actual cost, retrieved from the Item - Costing (ticpr0107m000) session.
- Tool resource type: tool's life unit, retrieved from the Tools (titrp0101m000) session.
Note:- You can modify the value in this field only if:
- The Resource Type field is set to Other
- The Resource Type field is set to Subcontracting and the Item is not specified or standard cost is not defined for the Item.
- Source
-
The source from which LN defaults the standard cost.
Allowed values
- Service
- Purchase
- Not Applicable
- Cost Amount
-
The cost amount of the resource requirement, calculated by the equation:
cost amount = quantity * unit cost
- Effective Time
-
The effective date and time.
- Expiry Time
-
The expiry date and time.
Note: If the current date has exceeded the expiry date, you cannot modify the resource requirement.