Master Routing for Site (tsacm1602m100)
Use this session to create and maintain master routings for the site.
- This session is displayed only if the Sites field is set to Active or In Preparation in the Implemented Software Components (tccom0100s000) session.
- LN defaults the data in this session from the Master Routings (tsacm1101m100) session only if the Use Global Definition check box is selected and you cannot modify this data.
Field Information
- Master Routing
-
The code of the master routing.
- Default
-
Indicates whether the master routing is set as the default.
Note:- You can use the Set as Default Master Routing option from the Action menu to modify (select/clear) the default settings.
- Site
-
The code of the site to which the master routing is assigned.
- Search Argument
-
The search key defined for the master routing.
- Use Global Definition
-
If this check box is selected, LN defaults the data specified in the Master Routing (tsacm1601m100) session and you cannot modify this data.
Note: By default, LN selects this check box if the Master Routing by Site is Mandatory check box is selected in the Activity Management Parameters (tsacm0100m000) session. - Activity Use
-
The scenario for which the master routing is used.
Allowed values
- Field Service
-
The reference activity can be used only for Field Service usage.
- Depot Repair
-
The reference activity can be used only for Depot Repair usage.
- General
-
The reference activity is not restricted to any particular usage and can be used generally. This activity can be used for Field Service and/or depot repair.
- Rental
-
The reference activity can be used only for Rental usage.
- Activity Group
-
The activity group to which the master routing is linked.
Note: This field is visible only if the Use Activity Groups check box is selected in the Activity Management Parameters (tsacm0100m000) session. - Subcontracted
-
If this check box is selected, a requirement of type subcontracting can be added to the master routing.
Note: You can create more than one requirement line of the type subcontracting for the master routing. - Buy-from Business Partner
-
The buy-from business partner who executes the subcontract work.
Note:- This field is enabled only if:
- The Subcontracted check box is selected.
- The Create Purchase Requisition check box is cleared.
- When a subcontracted reference activity is added to a subcontracted master routing, the Buy-from BP must be empty, or equal to the Buy-from BP of the master routing.
- This field is enabled only if:
- Supply Item to Subcontractor
-
If this check box is selected, the subcontracted item is supplied to the subcontractor warehouse.
Note:- This field is enabled only if:
- The Subcontracting with Material Flow field is selected in the Implemented Software Components (tccom0100s000)
- The Subcontracted check box is selected.
- The Activity Use is set to Depot Repair in the Master Routings (tsacm1101m100) session.
- This field is enabled only if:
- Supply Material to Subcontractor
-
If this check box is selected, the material linked to a subcontracted activity is supplied to the subcontractor.
- Create Purchase Requisition
-
If this check box is selected, purchase requisition can be generated as the subcontractor is not identified for the activity.
Note: This field is enabled only if the Subcontracted check box is selected. - Effective Time
-
The effective date and time.
- Expiry Time
-
The expiry date and time.
- Item
-
The item for which the master routing is defined.
- Functional Element
-
The functional element defined for the master routing.
Note: You can define functional elements only if the Functional Elements Active check box is selected in the General Service Parameters (tsmdm0100m000) session.