Using rental product to create planned equipment requests

  1. Create an equipment budget line in the Activity Budget (Equipment) (tpptc2112m000) session with the Equipment Type field set to Rental Product.
  2. Specify the equipment.
    Note: If the Equipment Type field is set to Rental Product, you can select an equipment from the Items - Project (tppdm0505m000) session.
  3. Generate the control data for the activity budget line using the Generate Control Data option from the Actions menu in theActivity Budget (tpptc2600m000) session. The budget line is displayed in the Control Data (Equipment Lines) (tpptc1537m000) session.
  4. Generate the budget cost analysis for the activity budget line using the Generate Budget Cost Analysis (tpptc3200m000) session. The budget data, grouped by cost types, is displayed in the Budgeted Project Costs (tpptc3540m000) session.
  5. Generate the planned PRP order for an activity line with a rental product using the Generate Planned PRP Orders (tppss6200m000) session.
    Note: You can view the related equipment request in the Planned Equipment Requests (tppss6125m000) session.
  6. Click the Transfer option in the Planned Equipment Requests (tppss6125m000) session to transfer the planned equipment request to Service .