EV Milestones Related Data (tpptc5515m000)

Use this session to maintain the milestones that are linked to the activity of a selected time-phased budget version and project. The EV-method related data of the milestones is stored in the same version.

Field Information

Project

The code that uniquely identifies the project.

Project Status

The project's status.

Current Version

The current version of the TP budget for the project.

Current Version

The status of the TP budget version.

Free

The data can be modified.

Actual

The data other than the total contract amount, management reserve, and the profit fee, can be modified.

Final

The amounts per activity or cost type in the Top Down Budget Data (tpptc5110s000) session cannot be modified.

Activity

The code that uniquely identifies the activity.

Activity

The status of the TP budget version.

Version

The current TP budget version.

Milestone

The code that uniquely identifies the milestone.

Text

If this check box is selected, the activity has an associated text, which you can view by clicking the Text button on the toolbar.