Generate Structure and Top-Down Budget (tpptc5210m000)
Use this session to link project activities to a top down budget version for a selected project. You can also generate the activity budget into a time-phased budget with a version for a selected project. The top down budget data is based on the activity budget.
If the generated budget amount exceeds the existing budget version amount:
- The contract amount is updated with the total of project contract amount plus extensions.
- If the budget amount remains more than the new contract amount (project contract amount plus extensions), the profit fee is decreased to balance the excess amount.
- If you do not want to update the version amount, you can discontinue the process.
Field Information
- Project
-
The From and To fields define a range of: projects.
- Version
-
The code that identifies the budget version.
- Description
-
The description or name of the code.
- Copy Activity Budget Lines
-
If this check box is selected, the activity-budget lines amounts are used to create the top down budget version amount.
- Only include Activities with Budget
-
If this check box is selected, only project activities for which budget is defined are considered for the calculation of the top-down budget version amount. An activity without a bottom-up budget is skipped when you create the top-down structure. Since a bottom-up budget can not be specified for the activities of type Planning Package, these activities are not available in the top-down structure.
Note: This check box is enabled only if the Copy Activity Budget Lines check box is selected. - If exceeding Budget Version Amount
-
If the activity budget amount exceeds the budget version amount, you can do the following:
Allowed values
- Continue
-
You can generate the top down budget version for the selected range of projects.
- Skip
-
You can skip the process.
Note: This field is enabled only if the Copy Activity Budget Lines check box is selected.For example, a project has a top activity and two child activities such as ACT1 and ACT2. The bottom-up budget amount for the top activity is $600, for ACT1 is $300, and for ACT2 is $300. A budget version also exists with budget $500 for the top activity, $300 for Activity1, and $200 for Activity2. Using the Generate Structure and Top-Down Budget (tpptc5210m000) session an activity structure is created with Top, ACT1, and ACT2 as part of the top-down structure. The total budget amount $600 is distributed first to the Top activity and later to the child activities ACT1 $300 and ACT2 $300. The total amount that is distributed, exceeds the budget version amount $500.
If the bottom-up amount is to be considered using the Copy Activity Budget Lines option, the budget amount for top activity totals to $600. This amount is more than the specified budget version amount of $500. LN calculates the profit amount of $100, which is a negative amount in this case. This amount is calculated only if the If exceeding Budget Version Amount field is set to Continue.