Budgeted Subcontracting Costs (tpptc3548m000)

Use this session to display the budgeted amounts and quantities of the cost-type, subcontracting, for:

  • The selected project code
  • The budget-cost analysis code

Field Information

Project

The code that uniquely identifies the project.

Project Status

The project's status.

Budget Cost Analysis Version

The code that uniquely identifies the budget-cost analysis.

Last Calculation Time

The date on which the latest budget-cost analysis was performed via the Generate Budget Cost Analysis (tpptc3200m000) session for the selected budget-cost analysis code.

Currency

The default currency in the overview session is the project currency. Both in a dependent and in an independent currency system you can change this currency to other currencies with the Rotate Currency option <CTRL-R>.

The following sequence is applicable:

  1. Project currency
  2. Local currency
  3. Reporting currency 1
  4. Reporting currency 2
Note: Only the last three currencies are home currencies.
Subcontracting

The code that uniquely identifies the subcontracting.

Reference Type

The nature of the subcontracting cost object.

Allowed values

Project

Specific to the selected project.

Standard

Common to all projects.

Quantity

The quantity of subcontracting.

Unit

The code that uniquely identifies the unit.

Amount

The total cost of the budget line.