Budgeted Extension Costs by Equipment Control Code (tpptc3537m000)
Use this session to list the budgeted extensions by equipment control code for:
- The selected project code
- The extension code
- The cost analysis version
Field Information
- Project
-
The code that uniquely identifies the project.
- Project Status
-
The project's status.
- Budget Cost Analysis Version
-
The code that uniquely identifies the cost analysis.
- Last Calculation Time
-
The date on which the latest budget-cost analysis was performed via the Generate Budget Cost Analysis (tpptc3200m000) session for the selected budget-cost analysis code.
- Extension
-
The code that uniquely identifies the extension.
- Currency
-
The default currency in the overview session is the project currency. Both in a dependent and in an independent currency system you can change this currency to other currencies with the Rotate Currency option <CTRL-R>.
The following sequence is applicable:
- Project currency
- Local currency
- Reporting currency 1
- Reporting currency 2
Note: Only the last three currencies are home currencies. - Control Code Equipment
-
The code that uniquely identifies the control code.
- Reference Type
-
The nature of the control code.
Allowed values
- Project
-
Specific to the selected project.
- Standard
-
Common to all projects.
- Equipment Quantity
-
The equipment quantity.
Note:- This field is enabled only if the Cost type is set to Equipment.
- This field is displayed only if the Services Procurement field is set to Active or In Preparation in the Implemented Software Components (tccom0100s000) session.
- This value must be specified if the Services Procurement field is set to Active in the Implemented Software Components (tccom0100s000) session.
-
The unit in which the equipment quantity is measured.
Note:- This field is enabled only if the Cost type is set to Equipment.
- This field is displayed only if the Services Procurement field is set to Active or In Preparation in the Implemented Software Components (tccom0100s000) session.
- Amount of Time
-
The amount of time for the equipment budgeted under the control code.
- Time Unit
-
The code that uniquely identifies the time unit.
- Amount
-
The total cost of the extension in the budget for the control code.