Budgeted Extension Costs by Labor Control Code (tpptc3536m000)

Use this session to list the budgeted extensions by labor control code for:

  • The selected project code
  • The extension code
  • The cost analysis version

Field Information

Project

The code that uniquely identifies the project.

Project Status

The project's status.

Budget Cost Analysis Version

The code that uniquely identifies the cost analysis.

Last Calculation Time

The date on which the latest budget-cost analysis was performed via the Generate Budget Cost Analysis (tpptc3200m000) session for the selected budget-cost analysis code.

Extension

The code that uniquely identifies the extension.

Currency

The default currency in the overview session is the project currency. Both in a dependent and in an independent currency system you can change this currency to other currencies with the Rotate Currency option <CTRL-R>.

The following sequence is applicable:

  1. Project currency
  2. Local currency
  3. Reporting currency 1
  4. Reporting currency 2
Note: Only the last three currencies are home currencies.
Control Code Labor

The code that uniquely identifies the control code.

Reference Type

The nature of the control code.

No. of Labor Hours

The number of labor hours budgeted for the extension under the control code.

Amount

The total cost of the extension in the budget for the control code.