Activity Budget (Labor) (tpptc2630m000)
Use this session to maintain skills that are linked to the task, for the activity budget. You can also maintain assignments that are linked to the budget line, for the activity budget.
- You can access this session from the Activity Budget (tpptc2600m000) session.
- The Required Skills for Activity Budget Lines (Labor) (tpptc2131m000) session is displayed as a satellite session. You can add and delete skills and modify the Skill Importance.
- The Assignments (tpptc2170m000) session is displayed as a satellite session. You can set assignments for the specific budget line.
- The Assignment tab is enabled only if you select the Use Assignments check box in the Project Planning Parameters (tppss0100s000) session.
Field Information
- Project
-
The code that uniquely identifies the project.
- Description
-
The description or name of the code.
- Status
-
The project status.
Allowed values
- Free
- Active
- Finished
- Closed
- Archived
- Plan
-
The code that uniquely identifies the plan.
- Description
-
The description or name of the code.
- Activity
-
The code that uniquely identifies the activity.
- Description
-
The description or name of the code.
- Status
-
The budget status of the activity.
Allowed values
- Free
-
The data can be modified.
- Actual
-
The data other than the total contract amount, management reserve, and the profit fee, can be modified.
- Final
-
The amounts per activity or cost type in the Top Down Budget Data (tpptc5110s000) session cannot be modified.
- Adjustment
-
If this check box is selected, the budget line linked to an adjustment
Note: If adjustment is specified for a budget line, the adjustment code is displayed along with the difference amount in the Extra Info group box. - Line
-
The code that uniquely identifies the line number.
-
An asterisk indicates that the budget line belongs to an adjustment.
- Task
-
The code that uniquely identifies the task.
- Description
-
The description of the task.
Note:You can select the code from one of these sessions:
- Tasks (tppdm0511m000)
- Project Tasks (tppdm6511m000)
- Reference Type
-
The reference type of the task. This indicates whether the control code is a standard or a project related task.
Allowed values
- Project
-
Specific to the selected project.
- Standard
-
Common to all projects.
- Labor Budget
-
- Budget
-
- Quantity
-
The number of labor units.
- Unit
-
The unit of measure used to express the number of labor hours.
- Description
-
The description or name of the code.
- Norm
-
The production time needed for the realization of a labor unit.
Norm is used in this calculation:
Number of hours = Quantity x Norm
Note:- This field is enabled only if the Budgeting Method is set to Labor Norms in the Project (tppdm6600m400) session.
- This field is disabled and the value is set to 1, If the Budgeting Method is set to Production Rate.
- Norm Unit
-
The unit of measure used to express the labor norm.
- Budget Status
-
The budget status.
Allowed values
- Free
-
The data can be modified.
- Actual
-
The data other than the total contract amount, management reserve, and the profit fee, can be modified.
- Final
-
The amounts per activity or cost type in the Top Down Budget Data (tpptc5110s000) session cannot be modified.
- Budget Date
-
The budget date that is used as the reference for currency transactions. By default, the budget date as specified for the project is added to the new budget lines.
- Text
-
If this check box is selected, a text is present.
- Assignment
-
- Employee
-
The code of the project employee linked to the activity budget. The code of the preferred project employee for the task that is linked to the activity budget. .
- Name
-
The name of the employee.
- Trade Group
-
The trade group to which the employee belongs to or the trade group that is required to complete the task.
- Description
-
The description or name of the code.
- Planning Factor
-
The number of employees required to carry out the task.
Note:- This value is defaulted from the Task (tppdm0615m000) or Project Task (tppdm6615m000) session. However, you can modify the value.
- This value is used in the Resource Management Workbench (tssoc8351m000) session for the planning and scheduling of the work order activities, service activities and project activities.
- Department
-
The code of the department. The Resource Management Workbench (tssoc8351m000) session displays relevant project assignments based on the department specified in this field.
Note: This value is defaulted from the Project Task (tppdm6615m000) session. In case, if the task is only available as a standard task, this value is defaulted from the Task (tppdm0615m000) session. However, you can modify the value. - Description
-
The description or name of the code.
- Start Date
-
The start date of the budget that is part of the project plan.
- Finish Date
-
The end date of the budget that is part of the project plan. The date is used when you update assignments for People. If you leave the date field empty, the assignment becomes recurrent.
- Costs
-
- Cost Rate
-
The cost amount for labor.
- Unit
-
The unit of measure in which the labor cost is expressed.
- /
-
The unit of measure in which the labor hour is expressed.
- Final Labor Rate
-
If this check box is selected, the labor cost is the final rate that is used for the activity budget.
- Cost Amount
-
The total labor cost amount of the activity budget.
- Unit
-
The unit of measure in which the cost amount is expressed.
- Home Amount
-
The total labor cost amount in home currency.
- Unit
-
The unit of measure in which the cost amount is expressed.
- Currency Rate/Rate Factor
-
The currency rate to convert the transaction currency to the home currency.
- Rate Factor
-
The rate factor.
- Contingency Amount
-
The provisional amount that includes the possible unexpected costs.
- Currency
-
The currency used for the contingency amount. The value is defaulted from the currency in which the Cost Amount is specified.
- Sales
-
- Sales Rate
-
The sales amount for labor.
- Unit
-
The unit of measure in which the sales price is expressed.
- Sales Amount
-
The total labor sales amount of the activity budget.
- Home Amount
-
The total labor sales amount in home currency.
- Unit
-
The unit of measure in which the sales amount is expressed.
- Currency Rate/Rate Factor
-
The currency rate to convert the transaction currency to the home currency.
- Rate Factor
-
The rate factor.
- Miscellaneous
-
- Related Details
-
- Seq. No. Subcontracting Line
-
The code of the subcontracting line number specified for the activity budget.
Note:If part of the required labor capacity is supplied by a subcontractor or labor agency, this field records the subcontracting line number in the budget.
The labor time for the subcontractor is specified in the Activity Budget (Subcontracting) (tpptc2113m000) session. The Cost Amount field for the labor line is then set to zero.
- Subcontracting
-
The code that uniquely identifies the subcontracting cost object.
- Description
-
The description or name of the code.
- Cost Component
-
The code that uniquely identifies the cost component linked to the activity budget.
Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session. - Description
-
The description or name of the code.
- Element
-
The code of the element.
- Sequence Number
-
The sequence number of the labor line linked to the element.
- Extension
-
The code of the extension.
- Description
-
The description or name of the code.
- Extra Info
-
- Budget Adjustment Code
-
The adjustment code.
These fields are also displayed, if adjustment is specified for the budget line.
- Difference amount: The difference amount based on the budget adjustment.
- Currency: The currency in which the difference amount is expressed.
- Quantity: The quantity specified for the activity. This value is defaulted from the Quantity field in the Activities (tppss2100m000) session.
- Amount of time: The time unit specified for the activity. This value is defaulted from the Number of Time Units field in the Activities (tppss2100m000) session.
- External Scheduling Package
-
- Calendar
-
The code that uniquely identifies the calendar linked to the activity budget.
- Calendar Description
-
The description or name of the code.
- Duration
-
The duration of the activity budget.
- Unit
-
The time unit in which the duration of the activity budget is expressed.
- Description
-
The description or name of the code.
- Service
-
- Service Related
-
If this check box is selected, the labor is linked to a service order.
- Project Assignments for Service Related Activities
-
If this check box is selected, project related assignments can be executed using Service and Project functionality. If this check box is cleared, project related assignments are executed by Service . Creating assignments using the Project functionality is blocked.
Note:- By default, this check box is selected.
- This check box is enabled only if:
- The Service Related check box is selected in the Activity Budget (Labor) (tpptc2111m000) session.
- The Use Assignments check box is selected in the Project Planning Parameters (tppss0100s000) session.
- Transferred to Service
-
If this check box is selected, the item is transferred to Service as a service order.