Control Data (Material Lines) (tpptc1535m000)

Use this session to view the generated budget lines of the material cost-type. The data includes results for both element and activity-based budgets.

Field Information

Project

The code that identifies the project.

Description

The description or name of the code.

Project Status

The project status.

Item

The code that identifies the item.

The code consists of a project code field and an item code field.

Item Description

The description or name of the code.

Sequence Number

The sequence number.

Quantity

The item's net quantity.

Unit

The unit of measure in which the quantity is expressed.

Currency

The home currency for the cost amount.

Cost Amount

The total cost of the budget line in the control data.

Cost Amount [%s]

The amount in the home currency.

Extension

The code that identifies the extension.

Description

The description or name of the code.

Extension Status

The status of the extension.

Plan

The code that uniquely identifies the plan.

Activity

The code that identifies the activity.

Description

The description or name of the code.

Budget Status

The budget status of the activity.

Cost Component

The code that identifies the cost component.

Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session.
Element

The code that identifies the element.

Description

The description or name of the code.

Budget Status

The budget status of the element.

Control Code

The control code of the item.

Effectivity Unit

The effectivity unit code. This is a display field.

Description

The description or name of the code.

Budget Line Number

The sequence number of the element or activity budget line for which the control data is generated.

Note: This field is used only if the Combine Requirements Planning On is set to Budget Line Level in the Project (tppdm6600m400) session.