Activity Relationships by Element (tpptc1202s000)

Use this session to update the activity-relationship data by element, so that you can draw up an activity budget from an element budget in the Copy Element Budget to Activity Budget (tpptc1240m000) session. The update can be performed for a budget line that has no plan and or activity of its own. The budget line will get the same plan and activity as entered here. You can also update existing plans and activities by checking the Overwrite Existing Activities field.

Field Information

Project

The project code.

Element

The element.

Plan

The plan from which the activities are selected.

Activity

The activity, for linking to the budget lines of the selected element.