Elements (tpptc1100m000)
Use this session to maintain an element for the selected project.
Field Information
- Project
-
The code that uniquely identifies the project.
- Description
-
The description or name of the code.
- Status
-
The project status.
- Element
-
The code that uniquely identifies the element.
- Budget Top Element
-
If this check box is selected, the element is considered as the top element and can be linked to the child elements.
- Layout Element
-
Indicates if the element is a layout element. The layout element can be used as heading to help make element budgets that use progress invoicing, well-organized.
Note: You can define the layout elements in the Layouts for Extra Elements (tpptc1101m000) session. - Element
-
- General
-
- Description
-
The description or name of the code.
- Text
-
If this check box is selected, a text is present.
- Search Key
-
The search key.
- Unit
-
The code that identifies unit of measure.
- Extension
-
The code that uniquely identifies the extension.
- Start Date
-
The planned start date and time for the execution of work with respect to the element.
- Finish Date
-
The planned finish date for the execution of work with respect to the element.
- Budget Status
-
The budget status of the element.
Note: If the status is Final and you add adjustments, you cannot change the status to Actual again.
- Control
-
- Physical Progress
-
If this check box is selected, you can register progress for the element. You can use the Physical Progress Level field to specify the level at which you want to record the progress of the project.
If this check box is cleared, you can maintain the progress for the element at a lower level in the budget structure.
- Physical Progress Level
-
The default level at which you want to register progress.
Allowed values
- Element
-
The project progress is recorded at the element level.
- Element / Control Code
-
The project progress is recorded at the element or control code level.
- Cost Control
-
If this check box is selected, costs entered on the budget lines for this element are transferred with the element to the control budget.
If this check box is cleared, the budget lines of the element are aggregated to the next higher level element which has been included in the budget structure as parent, and for which the cost control check box is selected.
Note: You can only maintain cost control for the element, if the element appears once in the budget structure. If the same element appears several times in the budget structure and the control budget check box is selected, LN gives a message and clears the check box. - Work Authorization Status
-
The work authorization status of the element.
- Reason
-
The reason for holding the work execution of the element. The field is enabled only when the Work Authorization Status field is set to On Hold.
- Description
-
The description or name of the code.
- Asset
-
- Asset
-
If this check box is selected, the element is assigned to a capital project.
Note: If an element is set to be capitalized, neither the child nor parent of the element can be capitalized. - Asset Number
-
The asset number.
Note: LN enables the asset number and extension fields only for projects of the type capital. - Description
-
The description or name of the code.
- Asset Extension
-
The asset extension number.
- Invoicing
-
- Progress Based Invoicing
-
Indicates whether the element can be invoiced.
- Progress for Invoice
-
The nature of the element.
You can maintain this field only if the Invoice Type field in the Contract Lines (tpctm1110m000) session is Progress Invoice in combination with the Progress based Invoicing field in the current session:
- If this field is set to Yes and the element is indirect, progress is booked on the direct element above this element. If the element is direct, the progress is booked on this element.
- If the field is set to Project Physical Progress, and the element is indirect, the progress is rolled down to this element.
- If the field is set to No, no progress is rolled down or booked on this element.
- Group Indirect Work
-
You can maintain this field only if the field Progr. Based Inv. is set to Project Phys. Progr. As a result, the Element Type field will become Indirect. This indicates the number of a group of costs that is related to indirect work.
For each group you can add up the costs on the progress invoice. In this way, you can show the total of indirect work by group, which is sometimes demanded by a principal.
The numbering of groups is free, but the groups are printed on the progress invoice in numeric order.
- Use Holdback
-
If this check box is selected, you can use holdback for this element.
- To be Settled
-
If this check box is selected, the cost of additional work (direct work) can be settled. This means that these costs are included in the progress invoice at a special settlement price.
If this check box is cleared, the cost of additional work (direct work) cannot be settled.
Note: Additional costs can only be settled if the Progress for Invoice field is set to Direct in the current session, and the Invoice Type field is set to Progress Invoice in the Contract Lines (tpctm1110m000) session. - Billable
-
If this check box is selected, the element costs are billed to the customer.
- Budgeting
-
- Budget Quantity
-
The budgeted number of elements. You need to enter a value only if you invoice by element.
If the element is part of an element structure, LN performs calculations with the frequency recorded via the Elements (tpptc1100m000) session. The frequency indicates the number of times the element appears in the project.
- Time Unit
-
The time unit that is linked to the element.
- Production Rate
-
The production rate expressed in quantities by time unit.
- Number of Time Units
-
The number of time units.
- Physical Progress Quantity
-
The value of this field is used for cost control; progress recording.
If the invoice method is Unit Rate or Progress for the project, the progress quantity must be filled. This quantity is the expected quantity that times the sales price can be invoiced. For a Unit Rate method the actual quantity can differ from the estimated quantity. For the Progress method, the progress must be equal to the physical progress quantity to be able to invoice the work.
- Pricing
-
- Sales Currency
-
The business partner currency.
- Sales Price
-
The unit sales price for the element.
You can maintain this field only if the Invoice Type field in the Projects (tppdm6100m000) session reads Progress Invoice or Unit Rate.
- Sales Price
- Currency Rate/Rate Factor
- Rate Factor Sales Price
- Settlement Currency
-
The home currency for the cost amount.
- Settlement Price
-
The unit price of additional work which may be charged during the progress invoicing procedure. This price may differ from the sales price for the budgeted work. The settlement price is printed under the heading additional work on the report in the Print Progress Invoice Specifications (tppin1410m000) session.
You can enter a value in this field only if the To be Settled check box is selected.
- Settlement Price
- Currency Rate/Rate Factor
- Rate Factor Settlement Price
- Miscellaneous
-
- Miscellaneous
-
- Priority Supply Warehouse
-
The warehouse that receives the deliveries for more than one project. The goods are sent from the priority supply warehouse to the project warehouse. The value is defaulted from the Priority Supply Warehouse field in the Projects (tppdm6100m000) session.
Note: For a project, when an activity is performed at multiple locations, it is easier to transfer goods when the warehouse is also defined at the Activity/Element level.ERP uses the following search path to check inventory, when generating PRP orders:
- The inventory in the Priority Supply Warehouse defined in the Activity (tppss2100m000) or Elements (tpptc1100m000) session.
- The inventory in the Priority Supply Warehouse defined in the Projects (tppdm6100m000) session.
- Description
-
The description or name of the code.
- Default Project Warehouse
-
The unique project warehouse code for the element.
- Sort Argument
-
The sort argument for sorting elements in the output of the reports, using the following sessions:
- The Print Principal's Project-Control Report (tpppc4412m000)
- The Print Project Manager's Control Report (tpppc4413m000)
This value is defaulted from the Sort Argument field in the Standard Element (tppdm0180s000) session. This value can be modified. Reports can be based on the selection of the sort argument.
- Service
-
- Reference Activity
-
The reference activity defined in Service that is linked to the project element.
Note: This value is defaulted from the Standard Element (tppdm0180s000) session when the project specific element is created based on the standard element. However, you can modify the value. - Description
-
The description or name of the code.
- Frequency
-
The number of times a reference activity is performed.
Note: This value is defaulted from the Standard Element (tppdm0180s000) session when the project specific element is created based on the standard element. However, you can modify the value. - Apply Frequency to
-
The method in which the frequency of a reference activity applies to the project element.
Allowed values
- Multiply Quantity
-
Indicates that the frequency is applied as a multiplier of the quantities of the reference activity.
- Not Applicable
- Create Service Order Activity
-
Indicates that additional service activities must be created.
- Create Service Order
-
Indicates that a service order must be created.
Note:- This field is enabled only if the value specified in the Frequency field is more than one.
- This value is defaulted from the Standard Element (tppdm0180s000) session when the project specific element is created based on the standard element. However, you can modify the value.