Budget Cost Surcharges by Labor (tpptc0521m000)

Use this session to display cost surcharges for a selected project that are based on labor lines.

Field Information

Project

The code that uniquely identifies the project.

Project Status

The project's status.

Sundry Cost

The code that uniquely identifies the sundry costs code.

Cost Component

The code of the cost component.

Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session.
Reference Type

The reference type of the budget cost surcharges by labor.

Allowed values

  • Project: Specific to the selected project.
  • Standard: Common to all projects.
Task

The code that uniquely identifies the labor.

Reference Type

The reference type of the budget cost surcharges by labor.

Allowed values

  • Project: Specific to the selected project.
  • Standard: Common to all projects.
Sequence Number

The code that uniquely identifies the sequence number.