Transfer Equipment Request to Planned PRP Purchase Order (tppss6252m000)
Use this session to transfer or convert a Planned Equipment Request to a
Planned PRP purchase order of the type Equipment.
Note:
- You can convert a Planned equipment request into a Planned PRP purchase order and a Planned PRP purchase order into a Planned equipment request only if the Equipment Code is present. For example, a crane or cabin that normally is internally provided but because of capacity issues, required to be hired externally as a part of the project.
- In the Order line balance, the Planned Equipment Request is replaced with the Planned PRP purchase order.
Field Information
- Planned Equipment Request
-
The unique code that identifies the planned equipment request.
- Project
-
The unique code that identifies the project.
- Description
-
The description or name of the code.
- Equipment
-
The equipment code.
- Description
-
The description or name of the code.
- Quantity
-
The quantity of the equipment.
Note: This field is enabled only if:- the Procurement by field of the purchase order is set to Service Procurement Order.
- Services Procurement is set to Active in the Implemented Software Components (tccom0100s000) session.
This value is defaulted from the Planned PRP Purchase Order.
- Amount of Time
-
The amount of time for which the equipment is ordered.
Note: This field is enabled only if the Procurement by of the Purchase Order is other than Equipment Procurement Order. - Time Unit
-
The unit of measure in which the amount of time is expressed.
- PRP Purchase Orders Number Group
-
The default number group defined for the planned PRP purchase order.
- Description
-
The description or name of the code.
- PRP Purchase Order Series
-
The default series defined for the planned PRP purchase order.
- Description
-
The description or name of the code.
- PRP Purchase Order
-