Planned PRP Purchase Order (Subcontracting) (tppss6112m000)
Use this session to maintain planned PRP purchase orders related to subcontracting.
Initially, the planned order date and the planned delivery date are set based on the control budget and the lead time. The planned delivery time is determined in the following way:
- If the control budget is of type Activity, the planned delivery time generated from the activity budget line.
- If the control budget is of type Element, the planned delivery time is generated from the element.
- If the requirement is caused by an extension and the extension date is later, the extension date becomes the planned delivery time.
- If no start date is found, the project planned delivery time is used.
- If a generated planned order time occurs in the past, it is changed to the current date. This will also shift the planned delivery time.
Field Information
- Project
-
The code that uniquely identifies the project.
- Description
-
The description or name of the code.
- Status
-
The current project status. The current project status. This status must be Free or Active, for all PRP orders in this session.
Allowed values
- Free
- Active
- Finished
- Closed
- Archived
- Order
-
The code that uniquely identifies the planned PRP equipment purchase-order.
If you create a new order, this field displays the chosen order series. If you save the PRP order, the first free number of the series is automatically allocated.
- Series Description
-
If the planned PRP purchase order is transferred, this series description is used to create the purchase order number.
- Planned Order
-
- Subcontracting Order
-
- Subcontracting
-
The code that uniquely identifies the subcontracting item.
- Reference Type
-
The planned PRP purchase order's reference type.
Allowed values
- Project
-
Specific to the selected project.
- Standard
-
Common to all projects.
- Cost Determination
-
Indicates how cost amounts related to the cost object are calculated in the actual budget.
Allowed values
- Quantity
-
The costs related to the subcontracting cost object are calculated, by quantity-based measure of productivity.
- Amount of Time
-
The costs related to the subcontracting cost object are calculated, by time-based measure of productivity. Example, the subcontractor can be paid by the hour.
- Rate Only
-
The costs related to the subcontracting cost object are calculated, based on only an agreed rate.
- Amount Only
-
The costs related to the subcontracting cost object are calculated, based on only an amount (lump sum).
Note: The field can be set to Rate Only or Amount Only only if:- The Services Procurement is set to In Preparation or Active in the Implemented Software Components (tccom0100s000) session.
- The Procurement by field is set to Subcontracting Procurement Order.
- Base Unit
-
The unit type used for cost determination.
Allowed values
- Not Applicable
- Quantity
- Time
Note:- This field is displayed only if the Services Procurement is set to Active or In Preparation in Implemented Software Components (tccom0100s000)session.
- This field is enabled only if the Cost Determination field is set to Amount Only or Rate Only.
- This field is set to Not Applicable if the Cost Determination field is set to Amount of Time or Quantity.
- This value cannot be modified when used for a planned PRP order or when costs are booked based on this value.
- Quantity
-
The ordered quantity.
Note: You can either use the Quantity or the Amount of Time for the cost determination of the subcontracting. This is based on the value specified in the Cost Determination field in the Project Subcontracting (tppdm6113s000) or the Subcontracting (tppdm0113s000) session. See: Cost Determination. - Unit
-
The unit of measure in which the quantity is expressed.
- Amount of Time
-
The number of time units for which the subcontracting is ordered.
Note: You can either use the Quantity or the Amount of Time for the cost determination of the subcontracting. This is based on the value specified in the Cost Determination field in the Project Subcontracting (tppdm6113s000) or the Subcontracting (tppdm0113s000) session. See: Cost Determination. - Time Unit
-
The unit of measure in which the amount of time is expressed.
- Ship-to Address
-
The ship-to code and description.
Note: This value is defaulted from the Address field in the Activities (tppss2100m000) session. If the address is not defined for the activity, the project address is used as the default ship-to-address. - Order Status
-
The current order's status. This shows the extent to which the order has been processed.
Allowed values
- Planned
-
The order can be either inserted manually or generated automatically. It will be replaced by the next generation run.
- Firm-Planned
-
The order cannot be changed or deleted by a subsequent generation run. It can however be manually changed.
- Approved
-
The order is protected from manual changes and also from the next generation run. Additionally, it can be transferred.
- Transferred
-
The planned purchase order can be handed over to a purchase order in Procurement .
- Canceled
-
The order is set to be deleted in the next generation run. (If the run is executed, this order is deleted unless you revise your decision).
- Order Text
-
If this check box is selected, a text is present.
- Business Partners
-
- Request for Quotation
-
If this check box is selected, LN creates a request-for-quotation (RFQ) instead of a purchase order.
Note: This check box is visible, only if the Requests for Quotation option is selected in the Procurement Parameters (tdpur0100m000) session. - Buy-from Business Partner
-
The code that uniquely identifies the buy-from business partner.
If this field is clear, and you transfer the PRP purchase order, LN creates a request for quotation (instead of a purchase order).
Note: When you modify the data in this field, the application displays a message to confirm the retrieval of the Purchase Price and Discount from the selected business partner. - Ship-from BP Description
-
The business partner's name.
- Ship-from Business Partner
-
The code that uniquely identifies the ship-from-business-partner.
- Cost Control
-
- Element
-
The code that uniquely identifies the element to which the cost object of this order belongs.
- Activity
-
The code that uniquely identifies the activity to which the cost object of this order belongs.
- Extension
-
The code that uniquely identifies the contract extension to which the cost object of this order belongs.
- Cost Component
-
The code that uniquely identifies the cost component of the cost object of this order.
Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session. - Extension
-
The sequence number of the element or activity budget line for which the control data is generated.
Note: This field is used only if the Combine Requirements Planning On is set to Budget Line Level in the Project (tppdm6600m400) session.
- Dates
-
- Planned Order Date
-
The planned date and time to order the purchase.
Click Procurement .
, to calculate the planned order time derived from the planned delivery time minus the order lead-times that are defined in - Start Time
-
The date and time when the subcontractor must start work.
- Finish Time
-
The date and time when the subcontractor is planned to finish work.
- Transaction Time
-
The transaction date and time for the planned purchase order.
- Planning
-
- Buyer
-
The code that uniquely identifies the buyer.
Note:- LN defaults the value when the planned PRP orders are generated, using the Generate Planned PRP Orders (tppss6200m000) session.
- When you specify a value in this field, LN checks if the specified employee’s data exists in the Employees - People (bpmdm0101m000) session and the employee is Active (based on the First Date of Employment and the Last Date of Employment). Else, a warning message is displayed. You can ignore the message.
- Name
-
The name of the buyer.
- Planner
-
The planner linked to the PRP purchase order (Subcontracting).
Note: LN defaults this value when the planned PRP orders are generated, using the Generate Planned PRP Orders (tppss6200m000) session. However, you can modify this value.
- Purchase
-
- Purchase
-
- Purchase Office
-
The purchase office that purchases subcontracting according to transferred PRP purchase orders.
- Purchase Type
-
The default purchase type. You can change the value or leave this field empty.
- Procurement by
-
The default option to indicate the type of procurement order that is generated for the cost object.
Allowed values
- Purchase Order
- Subcontracting Procurement Order
- Equipment Procurement Order
Note:- This field is displayed only if the Services Procurement is set toIn Preparation or Active in the Implemented Software Components (tccom0100s000) session.
- This field cannot be set to Purchase Order if the Cost Determination field is set to Amount Only or Rate Only.
- Services Trade
-
The code of the Services Trade used to categorize cost objects and to match the Buy-from Business Partner (supplier) during the requirements planning.
Note:- This field is displayed only if the Services Procurement is set to In Preparation or Active in the Implemented Software Components (tccom0100s000) session.
- You must specify this value if the Procurement by field is set to Equipment Procurement Order.
- The combination of Services Trade and Buy-from Business Partner must be valid.
- Must exist in the Services Trades (tcmcs2113m000) session.
- Must have the Nature of Supply Type set to Equipment.
- Description
-
The description or name of the code.
- Pricing
-
- Purchase Contract
-
The purchase contract (defined in Procurement ) according to which the item is purchased.
Note: This field is visible, only if the Contracts option is selected in the Procurement Parameters (tdpur0100m000) session. - Contract Line
-
The position number of the purchase contract to which the planned purchase order is related.
Note: This field is visible, only if the Contracts option is selected in the Procurement Parameters (tdpur0100m000) session. - Purchase Price
-
The currency of the purchase price of the planned purchase order.
- Purchase Price
-
Click the purchase price. The price is determined by the information in the Pricing module under Common .
button to calculate theIf the currency matches, you can retrieve prices from the price matrices. If there are no prices available in the matrices, LN looks at the contracts and then at the price of the cost object.
- Final Unit Cost
-
If this check box is selected, the purchase price is considered as the final price. However, if you modify the Purchase Price, the Price Origin is set to Manual.
- Price Origin
-
The origin of the price specified for the planned purchase order.
Allowed values
- Item Purchase Data
-
The sales price originates from the Items - Purchase (tdipu0101m000) session.
- Item Sales Data
-
The sales price originates from the Items - Sales (tdisa0501m000) session.
- Item Service Data
-
The sales price originates from the Items - Service (tsmdm2100m000) session.
- Supplier Price Book
- Default Price Book
-
The sales price originates from the default sales price book entered in the Price Books (tdpcg0111m000) field of the Pricing Parameters (tdpcg0100m000) session.
- Price Structure
-
The sales price originates from a price book linked to the Pricing Control (PCG) matrix of the price matrix type.
- Not Applicable
- External
-
The price originates from an external package.
- Generic Price List
- Manual
-
The sales price is entered manually.
- Contract
-
The sales price originates from a sales contract.
- Product Variant
-
The price originates from the Product Configuration module.
- Price from Derived Subcontracting
-
If this check box is selected, the price is retrieved from the subcontracting cost object.
- Discount
-
The discount percentage that is applicable for the planned purchase order.
Note: When you add or modify the data in this field, the Discount Origin field is set to Manual. - Discount Origin
-
The origin of the discount, as specified for the business partner on the planned purchase order.
Allowed values
- Contract
-
The discount originates from a purchase contract.
- Discount Structure
-
The discount originates from a Pricing Control (PCG) matrix of the type discount matrix. For more information, refer to Setting up a discount matrix.
- Price Book Discount Structure
-
The discount originates from the price book to which a discount schedule is linked.
- Project Equipment
-
The discount origin is based on the data specified in the project equipment.
- Standard Equipment
-
The discount origin is based on the data specified in the standard equipment.
- Project Subcontracting
-
The discount origin is based on the data specified in the project subcontracting.
- Standard Subcontracting
-
The discount origin is based on the data specified in the standard subcontracting.
- External
-
The discount originates from an external package.
- Manual
-
The discount is manually entered.
- Not Applicable
-
The discount is not applicable.
Note:This field is set to Manual, when you add or modify the data in the Discount field.
- Amount
-
The total price of the planned purchase order.
- Additional Information
-
- Additional Field
-
User-defined fields that can be linked to LN tables. Additional information fields do not add any specific value to LN as functional logic is not linked to the contents of these fields.
Note: When creating or generating the Planned PRP purchase order, LN defaults the additional information fields from the Contract Line, that is linked to the project peg of the planned order. - Text
-
- Text
-
The additional information related to subcontracting as part of the planned order.