Activity Workbench (tppss2600m000)

Use session to view and filter the activities. The activities can be filterd based on the Work Authorization Status, Due Date, Incomplete Labor Lines, and so on. This helps in identifying the activities that require immediate attention.
Note: 

For more information, see:

  • Activities (tppss2100m000)
  • When you access this session, the count for each filter is displayed as 0. You must use the Refresh Total option to view the updated counts.

Field Information

Selection
Project Manager

The name of the project manager.

Activity Manager

The name of the activity manager.

Project

The code of the project.

Project Location

The location of the project.

Period
Date From

The date and time from when the activities are displayed.

Date to

The date and time up to which the activities are displayed.

Due Date

The due date based on which the activities are filtered.

Allowed values

Scheduled Start Date
Scheduled Finish Date
Earliest Start Date
Latest Start Date
Earliest Finish Date
Latest Finish Date
Constraint Date
Work Authorization Status
On Hold

Click On Hold to activate this filter. The number of activities within the selection that are on hold, are displayed. LN selects the corresponding check box when you apply this filter.

Free

Click Free to activate this filter. The number of activities within the selection that are free, are displayed. LN selects the corresponding check box when you apply this filter.

Released

Click Released to activate this filter. The number of activities within the selection that are released, are displayed. LN selects the corresponding check box when you apply this filter.

Finished

Click Finished to activate this filer. The number of activities within the selection that are finished, are displayed. LN selects the corresponding check box when you apply this filter.

Closed

Click Closed to activate this filer. The number of activities within the selection that are released, are displayed. LN selects the corresponding check box when you apply this filter.

Due Date
Past Due

Click Past Due to activate this filter. The activities for which the scheduled start date is before the current date, are displayed. LN selects the corresponding check box when you apply this filter.

Today

Click Today to activate this filter. Activities for which the scheduled start date is the current date, are displayed. LN selects the corresponding check box when you apply this filter.

1 - 7 days

Click 1 - 7 days to activate this filter. Activities for which the scheduled start date is within 1 to 7 days from the current date, are displayed. LN selects the corresponding check box when you apply this filter.

Beyond 7 days

Click Beyond 7 days to activate this filter. Activities for which the scheduled start date is 8 or more days from the current date, are displayed. LN selects the corresponding check box when you apply this filter.

No Date

Click Beyond 7 days to activate this filter. Activities for which date is not specified, are displayed. LN selects the corresponding check box when you apply this filter.

Incomplete Labor Lines
Allocated Hours

Click Allocated Hours to activate this filter. Activities for which hours are allocated, are displayed. LN selects the corresponding check box when you apply this filter.

Assignments

Click Assignments to activate this filter. Assignments with the status Free, are displayed. LN selects the corresponding check box when you apply this filter.

Not Approved
PRP Purchase Orders

Click PRP Purchase Orders to activate this filter. Activities for which the linked PPR purchase orders are required to be approved, are displayed. LN selects the corresponding check box when you apply this filter.

PRP Warehouse Orders

Click PRP Warehouse Orders to activate this filter. Activities for which the PPR warehouse orders are required to be approved, are displayed. LN selects the corresponding check box when you apply this filter.

Graph

The graphical representation of the data is displayed in the grid. This data is displayed as a mix of a stacked and a standard bar graph.

Note: You can select Costs or Hours to view the data in the graph. The data in the graph is displayed based on the period specified in the Project Accounting Parameters (tpppc0100s000) session and Monitoring data (that requires Build Actual Cost Control (tpppc4803m000)) to get the up-to-date data.