Print Activity Baselines (tppss2420m000)
Use this session to print a selected range of activity baselines (planning).
Field Information
- Project
-
The From and To fields define a range of: projects.
- Project Selection
-
The From and To fields define a range of: projects.
- Baseline
-
The From and To fields define a range of: baselines (planning).
- Baseline
-
The From and To fields define a range of: baselines (planning).
- Activity
-
The From and To fields define a range of: activities.
- Activity
-
The From and To fields define a range of: activities.
- Tracking Data
-
If this check box is selected, LN prints the tracking data report of the project. The baseline start and finish dates can be compared to the actual start and finish date to evaluate the accuracy of the baseline dates.
- Milestones
-
If this check box is selected, LN prints the Milestones.