External Scheduling OBS (tppss2136m000)
Use this session to view the organization breakdown structure (OBS) related project data that is linked to the external scheduling package.
The data in this session is populated from the External Scheduling Interface (tppss2231m000) session, when you import/ export the LN project data from/ to an external scheduling interface.
Field Information
- Project
-
The code of the project for which the external scheduling package is used.
- Description
-
The description or name of the code.
- Plan
-
The plan that must be used for the import or export of the project data to or from an external scheduling package.
- Description
-
The description or name of the code.
- Connection Node
-
The activity or node of the Infor LN Project (related to OBS) that must be connected to the activity or node of a project in the external scheduling package. If you link a complete project in LN to a project in the external scheduling package, this node is not specified.
- Description
-
The description or name of the code.
- OBS Code
-
The code of the organization breakdown structure linked to the project.
- OBS Element
-
The organization breakdown structure (OBS) element that is linked to the project.
- OBS Element description
-
The description or name of the code.
- ESP Reference
-
The reference number linked to the external scheduling package (ESP).
- Synchronization Status
-
The status of the synchronization of the LN project data with the external scheduling package.
Allowed values
- Synchronized
- Delete
- Modify
- New
- Initial