Performance Measurement OBS (tpppc5560m000)

Use this session to list performance measurement data for a project at the organization breakdown structure (OBS) level.

Field Information

Project

The project code.

Generate Code

The generated codes store information about the generation of performance measurement data.

Currency

The currency that is displayed is one of the home currencies. In performance measurement the currency array can be four deep. If you use an independent currency system you can rotate between four currencies. In a dependent situation you can rotate between the project and the home currencies.

Currency

The currency.

OBS Element

The OBS element to which the data belongs.

Cost Control Period

The year in which the transaction must be posted to the project history for cost control. The default value of this field is the year of the date of input's cost-control period.

If the Cost Control Period = Fiscal Period check box in the Project Accounting Parameters (tpppc0100s000) session is selected, the current fiscal year is the default value for this field.

Cost Control Period

The period.

Planned Value

The period amount of scheduled work.

Earned Value

The period amount of performed work.

Actual Cost

The period amount of actual work.

Schedule Variance

The schedule variance is calculated as follows: Performed - Scheduled Work

Cost Variance

The cost variance is calculated as follows: Performed- Actuals.

EAC

The estimated amount at completion, accumulated by period.