Performance Measurement Activity/Cost Type (tpppc5541m000)

Use this session to list performance measurement data for a project at the activity cost type level.

Note: If you have started this session by zooming, you can only find and select a record.

Field Information

Project

The project code.

Generate Code

The generated codes store information about the generation of performance measurement data.

Activity

The activity code.

Currency

The currency that is displayed is one of the home currencies. In performance measurement the currency array can be four deep. If you use an independent currency system you can rotate between four currencies. In a dependent situation you can rotate between the project and the home currencies.

Currency

The currency.

Cost Type

cost type

Cost Control Period

The year in which the transaction must be posted to the project history for cost control. The default value of this field is the year of the date of input's cost-control period.

If the Cost Control Period = Fiscal Period check box in the Project Accounting Parameters (tpppc0100s000) session is selected, the current fiscal year is the default value for this field.

Cost Control Period

The cost-control period.

Planned Value

The period amount of scheduled work.

Earned Value

The period amount of performed work.

Actual Cost

The period amount of actual work.

Schedule Variance

The schedule variance is calculated as follows: Performed - Scheduled Work

Cost Variance

The cost variance is calculated as follows: Performed - Actuals

Actual Cost

The actual work amount.

Cost Variance

The cost variance amount.

Planned Value

The scheduled work amount.

Earned Value

The performed work amount.

Actual Cost

The actual work amount.

Schedule Variance

The scheduled variance amount.

Cost Variance

The cost variance amount.

Actual Cost

The actual work amount.

Cost Variance

The cost variance amount.

BAC

The amount of budget at completion.

EAC

The estimated amount at completion.

Variance at Completion

The VAC (Variance at Completion).