Approve Commitments (Material) (tpppc4580m000)

Use this session to confirm material commitments before posting by the Process Transactions (tpppc4802m000) session.

These commitments are derived from the Commitments (Material) (tpppc2110s000) session.

Field Information

Posted

If this check box is selected, the commitment is posted to Financials .

Approved for Posting

If this check box is selected, the transaction can be processed in Financials and/or in the project history of Project .

Project

The code that identifies the project.

Item

The item code.

Sequence

A number that identifies a commitment.

Element

The element code.

Activity

The code that identifies the activity.

Currency

currency

Cost Amount

The total costs. You can change the cost amount, which is computed by LN in the Commitments (Material) (tpppc2110s000) session. LN then automatically adjusts the unit cost.

Registration Date

Date of input for the forecast deviation of costs.

Posting Type

The posting type.