Control by Project/Cost Type (tpppc4511m000)

Use this session to monitor the projects that are executed. The actual cost control is aggregated at the project/cost type level.

This is one in a range of sessions that are available in the Project Progress module for monitoring projects. Each of these sessions provides a different level of detail.

Note: If you have started this session by zooming, you can only find and select a record.

Field Information

Project

The code that identifies the project.

Main Project Total Cost Indicator

Indicates whether the data relates to the project itself or to the project and its underlying subprojects.

Generated

The date on which the current project cost control was built. The value of this field is updated by the Build Actual Cost Control (tpppc4803m000) session.

Currency

The default currency in the overview session is the project currency. Both in a dependent and in an independent currency system you can change this currency to other currencies with the Rotate Currency option <CTRL-R>.

The following sequence is applicable:

  1. Project currency
  2. Local currency
  3. Reporting currency 1
  4. Reporting currency 2
Note: Only the last three currencies are home currencies.
Currency

The currency description.

Cost Type

The cost type.

Total Budget

The budgeted amount as shown in the control data.

Earned Value

The performed at the end of the current period.

Note: For exceptions on this calculation see: How LN calculates the performed.
Incl. Commit Actual

The actual amount including commitments.

Incl. Commit. Variance

The amount that is spent (in this period) including commitments.

Total spent = Actual Costs (This Period)+ Commitments (This Period)

Excl. Commit Actual

The actual costs (excluding the commitments), which are posted to the history for all periods up to the current one.

Excl. Commit. Variance

The result's amount excluding commitments.

Budget Quantity

The total budgeted quantity shown in the control data.

Earned Value

The quantity that is allowed at the end of the current period.

Incl. Commit Actual

The actual amount including commitments.

Incl. Commit. Variance

The amount that is spent (in this period) including commitments.

Total spent = Actual Costs (This Period) + Commitments (This Period)

Excl. Commit Actual

The total quantity of the cost transactions (excluding the anticipated payments), which are posted to the history for all periods up to the current one.

Excl. Commit. Variance

The result's amount excluding commitments.

Current Period

The year of the actual cost-control period.

/

The period for actual cost control.

Incl. Commit Actual

The actual amount including commitments.

Incl. Commit. Earned Value

The costs that you can incur in the current period.

Incl. Commit. Variance

The amount that is spent (in this period) including commitments.

Total spent = Actual Costs (This Period) + Commitments (This Period)

Excl. Commit Actual

The actual costs (excluding the commitments), which are posted to the history for the current period.

Excl. Commit. Earned Value

The performed excluding commitments.

Excl. Commit. Variance

The result's amount excluding commitments.

Incl. Commit Actual Quantity

The actual quantity including commitments.

Excl. Commit. Earned Value

The quantity that can be produced within the current period.

Incl. Commit. Variance

The result including commitments.

Excl. Commit. Actual Quantity

The cost transaction's total quantity (excluding the anticipated payments), that are posted to the history for the current period.

Excl. Commit. Variance

The result excluding commitments.

Actual Cost

The actual amount.

Variance

The result amount.

Forecast Cost

The additional cost forecast for the end of the project that is anticipated at the end of the current period.

Variance at Completion

The final result that is forecast.

Forecast Quantity

The additional quantity forecast for the end of the project as anticipated for the end of the current period.

Variance at Completion

The final result that is forecast.