Print Project Control (tpppc4420m000)

Use this session to print project control, purchase control, and order-control reports. Reports can be based on project, project/element, project/activity, and project/extension.

The levels at which cost control is generated are selected in the Project - Cost Control Levels (tppdm6102m000) session.

Field Information

Report Type

The type of report you want to print.

Allowed values

Project Control
Purchase Control
Order Control
Level to be Printed

The level on which the data is printed. The levels at which cost control is generated are selected in the Project - Cost Control Levels (tppdm6102m000) session.

Period to

The year up to which the level is to be printed.

/

The period to which the level is to be printed.

Sort By

Indicates how you want to sort the level.

Sort Project by

Indicates how you want the project to be sorted.

Material

If this check box is selected, this cost control cost type is printed.

Labor

If this check box is selected, this cost control cost type is printed.

Equipment

If this check box is selected, this cost control cost type is printed.

Subcontracting

If this check box is selected, this cost control cost type is printed.

Sundry Cost

If this check box is selected, this cost control cost type is printed.

Break-Down Lines

If this check box is selected, the project breakdown-lines are printed.