Print Cost Control (tpppc4411m000)

Use this session to print cost-control reports. Reports can be based on project, element, activity and extension by cost type, cost component, and control code.

The levels at which cost control is generated are selected in the Project - Cost Control Levels (tppdm6102m000) session. Various criteria, to make a selection of the projects and the information to be printed, are also available in this session.

Performance aspects

The settings in this session could affect system performance and database growth. For more information, refer to Print actual costs

Field Information

Period to

The report year.

/

The report period.

Final Result Forecast

If this check box is selected, the final result forecast is printed.

Process Extension Lines

If this check box is selected, the extension lines are processed.

Commitments

If this check box is selected, the commitments are considered costs.

Aggregate Subprojects to Main Project

Aggregate the costs of the sub project to the main project.

Sort By

The report's sort sequence.

Material

If this check box is selected, this cost control cost type is printed.

Labor

If this check box is selected, this cost control cost type is printed.

Equipment

If this check box is selected, this cost control cost type is printed.

Subcontracting

If this check box is selected, this cost control cost type is printed.

Sundry Cost

If this check box is selected, this cost control cost type is printed.