Cost Surcharges by Cost Type (tpppc2581m000)

Use this session to list cost surcharges for a combination of the project, the cost type, and the surcharge code.

Note: If you have started this session by zooming, you can only find and select a record.

Field Information

Project

The code that identifies the project.

Project Status

The project status.

Cost Type

cost type

The cost type to which the surcharge must be posted.

Allowed values

Labor

The overheads are calculated for Labor cost type.

Overhead

The overheads are calculated for Overhead cost type.

Materials

The overheads are calculated for Material cost type.

Equipment

The overheads are calculated for Equipment cost type.

Subcontracting

The overheads are calculated for Subcontracting cost type.

Sundry Costs

The overheads are calculated for Sundry cost type.

Sundry Cost

The sundry costs code

Sequence Number

The sequence number code.Uniquely identifies the surcharge.

Percentage

The surcharge percentage specified for the cost to calculate the surcharge amount.

Posting Method Finance

Indicates the process to post surcharges to Financials , following the registration of costs and revenues.

Element

The element code to which the calculated surcharge must be posted. If you leave this field blank, the surcharge is posted to the element under which the cost, on which the surcharge is calculated, has been recorded.

Cost Component

The cost component to which the surcharge is posted.

Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session.