Material Cost Forecast (tpppc2516m000)
Use this session to display cost forecasts for the combination of the project and the registration date for the different item codes.
These values are used to compute forecast amounts in control enquiries and report sessions.
Field Information
- Project
-
The project code.
- Description
-
The description or name of the code.
- Project Status
-
The project status.
- Registration Date
-
The date of input for the forecast deviation of costs.
- Item
-
The item code.
- Element
-
The element code.
- Description
-
The description or name of the code.
- Work Authorization Status
-
The work authorization status of the element.
- Activity
-
The activity code.
- Description
-
The description or name of the code.
- Work Authorization Status
-
The work authorization status of the activity.
- Currency
-
The transaction currency
- Estimated Extra Costs
-
The amount is the estimated extra costs on top of your current budget.
- Estimate to Complete
-
The expected additional cost needed to complete an activity or project.
- Estimate at Completion
-
The estimated cost at completion value is used to determine the cost at the end of a project.
- Approved
-
The confirmed forecasted cost amount.
- Cost Component
-
The cost component associated with the cost object.
Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session.