Compare Commitments with Actual Costs (tpppc2412m000)

Use this session to print the commitment data and the actual costs for a specified range of project, element, activity, the purchase order number and the buy-from business partner.

Field Information

Buy-from Business Partner

The From and To fields define a range of: buy-from business partners for which the commitment and cost data must be printed

Order Number

The From and To fields define a range of: the purchase orders for which the commitment and cost data must be printed

Project

The From and To fields define a range of: the projects for which the commitment and cost data must be printed

Element

The From and To fields define a range of: the elements for which the commitment and cost data must be printed

Activity

The From and To fields define a range of: the activities for which the commitment and cost data must be printed

Description

The description or name of the code.

Minimum commitment amount

The allowed difference between the anticipated payments and the actual costs. Only commitments for which the difference between the commitments and the costs is greater than the specified value, are printed.

Sort By

The report's sort sequence.