Cost Surcharges by Cost Component (tpppc2182s000)
Use this session to maintain the cost surcharges for the combination of the project, the cost component and the surcharge code.
Field Information
- Project
-
The code that identifies the project.
- Description
-
The description or name of the code.
- Project Status
-
The project status.
- Cost Component
-
The cost component.
Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session. - Sundry Cost
-
The sundry costs code
- Sundry Cost
-
The cost object code.
- Sequence Number
-
The sequence number code.
- Percentage
-
The surcharge amount, expressed as a percentage.The surcharge percentage.
- Element
-
The code that uniquely identifies the element to which the surcharge amount is posted.
- Description
-
The description or name of the code.
- Plan
-
The code that uniquely identifies the plan. The plan includes the activity to which the surcharge is posted.
- Activity
-
The activity that the surcharge is posted to.
- Description
-
The description or name of the code.
- Cost Component (Control)
-
The cost component to which the surcharge is posted. If you leave this field blank, the surcharge is posted to the cost component that contains the costs based on which the surcharge is calculated.
- Description
-
The description or name of the code.
- Extension
-
The extension code.
- Description
-
The description or name of the code.
- Posting Method Finance
-
Indicates how surcharges are to be processed from the registration of costs and revenues in Financials .
- Fixed Enterprise Unit
-
The enterprise unit for which the surcharge is computed. If the Posting Method Finance field in the Revenue Surcharges by Project (tpppc2185s000) session is set to Fixed Enterprise Unit, this unit can be maintained.
- Effective Date
-
The date from which the surcharge is effective.
- Expiry Date
-
The expiry date for the surcharge that is entered.