Cost Surcharges by Cost Type (tpppc2181s000)

Use this session to maintain the cost surcharges for the combination of the project, the cost type and the surcharge code.

Field Information

Project

The project code.

Description

The description or name of the code.

Project Status

The project status.

Cost Type

The cost type to which the surcharge must be posted.

Sundry Cost

The sundry costs code

Sundry Cost

The cost object code.

Sequence Number

The sequence number code.

Percentage

The surcharge percentage specified for the cost to calculate the surcharge amount.

Element

The code that uniquely identifies the element to which the surcharge amount is posted.

Description

The description or name of the code.

Plan

The code that uniquely identifies the plan. The plan includes the activity to which the surcharge is posted.

Activity

The activity that the surcharge is posted to.

Description

The description or name of the code.

Cost Component

The cost component to which the surcharge is posted. If you leave this field blank, the surcharge is posted to the cost component that contains the costs based on which the surcharge is calculated.

Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session.
Description

The description or name of the code.

Extension

The extension code.

Description

The description or name of the code.

Posting Method Finance

Indicates the process to post surcharges to Financials , following the registration of costs and revenues.

Fixed Enterprise Unit

The enterprise unit for which the surcharge is computed. If the Posting Method Finance field in the Revenue Surcharges by Project (tpppc2185s000) session is set to Fixed Enterprise Unit, this unit can be maintained.

Effective Date

The date from which the surcharge is effective.

Expiry Date

The expiry date for the surcharge that is entered.