Physical Progress by Extension/Labor (tpppc1582m000)
Use this session to list the progress for the combination of the extension and the labor cost object.
Field Information
- Project
-
The project code.
- Project Status
-
The project status.
- Date
-
The date for which forecast will be generated.
- Prog. Reg. Level
-
This field indicates whether the progress for the cost type Labor is recorded in project monitoring by cost object or control code.
- Extension
-
The extension code.
- Extension Type
-
The status of the extension.
- Extension Status
-
The status of the extension.
- Task
-
The labor's code.
- Budget Quantity
-
The total budgeted quantity shown in the control data.
- Reported Completed
-
If this check box is selected, the production of the selected element is assumed to be completed. If it is not completed, you can still enter a progress.
- Phys. Progress [%]
-
The progress of the selected cost object or control code, expressed as a percentage of the total budgeted quantity or time.
- Phys. Progress [Qty.]
-
The progress of the selected cost object or control code, expressed as a quantity or amount of time.