Physical Progress by Extension/Material (tpppc1580m000)

Use this session to list progress for the combination of the extension and the material cost object.

Field Information

Project

The project code.

Project Status

The project status.

Date

The date for which forecast will be generated.

Prog. Reg. Level

The level at which you can record the progress for this cost type.

Extension

The extension code.

Extension Type

The extension status.

Extension Status

The extension status.

Item

The item's code.

Budget Quantity

The total budgeted quantity as shown in the control data.

Reported Completed

If this check box is selected, the production of the selected element is assumed to be completed. If it is not completed, you can still enter a progress.

Phys. Progress [%]

The progress of the selected cost object or control code, expressed as a percentage of the total budgeted quantity or time.

Phys. Progress [Qty.]

The progress of the selected cost object or control code, expressed as a quantity or amount of time.