Physical Progress by Element/Labor (tpppc1522m000)

Use this session to list progress for a combination of the element and the labor cost object, which allows you to monitor the result in the Project Progress module.

Field Information

Project

The project code.

Description

The description or name of the code.

Project Status

The project's current status.

Prog. Reg. Level

This field indicates whether the progress for the cost type Labor is recorded in project monitoring by cost object or control code.

Element

The element code.

Description

The description or name of the code.

Work Authorization Status

The work authorization status of the element.

Task

The labor code.

If the Labor Phys. Progress field in the Projects (tppdm6100m000) session is set to Cost Object, you can select a budgeted cost object.

If the field is set to Control Code, you can select the control code of a budgeted cost object.

Description

The description or name of the code.

Budget Quantity

The total budgeted quantity shown in the control data.

Reported Completed

This field indicates whether the selected cost object has been reported as completed.

A cost object can be reported as completed even if the progress is not 100%, as shown in the following example.

In the Planning module you have budgeted 100 cubic meters of soil. However, only 80 cubic meters of soil need to be deposited. Once the work is ready, select this field and enter 80% in the Phys. Progress [%] field because you only require 80% of the total budgeted quantity.

If the progress is not 100%, the difference when compared to the budget can be settled, if:

  • To be Settled check box in the Elements (tpptc1100m000) session is selected for the selected element.
  • The selected cost object belongs to an extension for which the Extension Type field in the Extension (tpptc0110s000) session is set to Quantities to be Settled.
Phys. Progress [%]

The progress of the selected cost object or control code expressed as a percentage of the total budgeted quantity or time.

You can maintain this field for the selected cost object or project only if the Register Progress field in the Projects (tppdm6100m000) session is set to Yes.

The value of the above field does not have an influence if the Reported Completed check box is not selected. You can always enter the progress.

If the Physical Progress > 100% Allowed check box in the Project Accounting Parameters (tpppc0100s000) session is selected, you can enter a progress greater than 100%.

Example

In the Planning module you budgeted 100 cubic meters of soil. However, you deposited an additional 20 cubic meters. In this case, you enter 120%.

Phys. Progress [Qty.]

The progress of the selected cost object or control code expressed as a quantity or amount of time.

Date

The date on which the progress is recorded.