Print Physical Progress Form by Element/Cost Object (tpppc1421m000)
Use this session to print a form showing progress details for a combination of element and cost object. Each form shows the budget, the current progress, and the previous progress.
You can then use this form for recording details on site. You can enter the current progress in the work center manually, either daily or weekly, and re-enter them later into the relevant session.
Field Information
- Material
-
If this check box is selected, LN prints progress for the item cost object.
- Labor
-
If this check box is selected, LN prints progress for the labor cost object.
- Equipment
-
If this check box is selected, LN prints progress for the equipment cost object.
- Subcontracting
-
If this check box is selected, LN prints progress for the subcontracting cost object.
- Sundry Cost
-
If this check box is selected, LN prints progress for the sundry cost cost object.