Generate Physical Progress by Extension/Cost Object (tpppc1188m000)
Use this session to update the progress of extensions at the extension level or at the cost object level (determined from the progress registration level).
Field Information
- Project
-
The code that identifies the project.
- Description
-
The description or name of the code.
- Project Status
-
The project status.
- Physical Progress Date
-
The date for which progress will be generated.
- Material
-
If this check box is selected, progress data is generated for the item cost object.
- Material
-
The progress percentage of the item cost object.
- Labor
-
If this check box is selected, progress is generated for the labor cost object.
- Labor
-
The progress percentage of the labor cost object.
- Equipment
-
If this check box is selected, progress is generated for the equipment cost object.
- Equipment
-
The progress percentage of the equipment cost object.
- Subcontracting
-
If this check box is selected, progress is generated for the subcontracting cost object.
- Subcontracting
-
The progress percentage of the subcontracting cost object.
- Sundry Cost
-
If this check box is selected, progress is generated for the sundry cost cost object.
- Sundry Cost
-
The progress percentage of the sundry cost cost oject.
- Reported Completed
-
If this check box is selected, master lines are generated independently from the value of the Register Progress field for the project or the cost object.
- Delete Existing Data
-
If this check box is selected, the progress that is newly generated for existing lines replaces the old generated control data progress of these lines. What remains is the new progress.
If this check box is cleared, LN will leave the lines that were deleted after generating control data in tact in the history when you generate new progress here. For lines that new progress is generated for, the old lines will be updated.
- Record Physical Progress
-
Use this field to choose how to record stages.