Generate Physical Progress by Activity/Cost Object (tpppc1148m000)

Use this session to globally update the progress of activities at the activity level or at the cost object level (determined from the progress registration level). You can monitor the result in the Project Progress module.

Field Information

Project

The code that identifies the project.

Project Status

The project's current status.

Physical Progress Date

The date for which the progress is generated.

Material

If this check box is selected, LN generates progress for the item cost object.

Material

The progress percentage for the item cost type.

Labor

If this check box is selected, LN generates progress for the labor cost object.

Labor

The progress percentage of the labor cost object.

Equipment

If this check box is selected, LN generates progress for the equipment cost object.

Equipment

The progress percentage for the equipment cost type.

Subcontracting

If this check box is selected, LN generates progress for the subcontracting cost object.

Subcontracting

The progress percentage for the subcontracting cost type.

Sundry Cost

If this check box is selected, LN generates progress for the sundry cost t cost object.

Sundry Cost

The progress percentage for the sundry cost cost type.

Reported Completed

If this check box is selected, master lines are generated independently from the value of the Register Progress field in the Projects (tppdm6100m000) for the project or the cost object.

Delete Existing Data

If this check box is selected, the progress that is newly generated for existing lines replaces the old generated control data progress of these lines. What remains is the new progress.

If this check box is cleared, LN will leave the lines that were deleted after generating control data in tact in the history when you generate new progress here. For lines that new progress is generated for, the old lines will be updated.

Record Physical Progress

Use this field to choose how to record the progress.