Working with the Project 360 (tppdm6500m100) session
Use this session to perform project related tasks and retrieve project-related data. You can view and maintain project information, such as costs, revenue, budget, estimates, and progress.
For a project selected from the list, the check boxes in the Contract, Scope, Progress, Estimate, Budget, Quality, Control, and Requirements group boxes indicate if related data is maintained. You can click the entity to view the corresponding session, wherein you can view and maintain the related data.
- Performance, Payment and Receipts, and Hours group boxes display project related data, if maintained. : The tiles in the
- Revenues and Costs donuts
display the net amount of revenue and costs for the selected project. You can click
the donut to view the corresponding session, wherein you can view the related
transactions. Note:
- These options are displayed for the Revenues donut: Revenues and Forecast Extra Revenues.
- These options are displayed for the Costs donut: Commitments and Costs.
: The - Budget vs. Forecast group box. : The Budget, Commitments, ETC, and Actuals data for the selected project is displayed in a graphical format in the
Field Information
- Filter
-
- Project Manager
-
The employee who is the manager for the project.
- Description
-
The description or name of the code.
- Project Management Office
-
The code of the project management office.
-
The description or name of the code.
- Estimate/Budget
-
- Estimate
-
The estimate for the project.
- Budget
-
The budgeted amount for the project.
- Budget Number of Hours
-
The number of labor hours budgeted for the project.
- Revenues
-
- Revenues
-
The revenues of the project that are posted to the history for all periods up to the current one.
- Forecast Extra Revenues
-
The additional revenue that is forecast for the end of the project and is anticipated at the end of the current period.
- Received From Customer
-
The amount received from the customer against sales invoices. This is the amount displayed in the Invoice-to Business Partner Open Entries (tfacr2520m000) session in Financials .
Note: The Supplier payment is a settlement against this open entry and not against a specific invoice line. An open entry comprises many invoice lines which may or may not be linked to the same project. Hence, the amount overdue on a project cannot be determined correctly until the received amount information against the specific invoice line is stored in LN Financials . - Customer Outstanding
-
The amount due to the customer to be paid against the sales invoices. This is the amount displayed in the Invoice-to Business Partner Open Entries (tfacr2520m000) session in LN Financials .
Note: The Supplier payment is a settlement against this open entry and not against a specific invoice line. An open entry comprises many invoice lines which may or may not be linked to the same project. Hence, the amount overdue on a project cannot be determined correctly until the received amount information against the specific invoice line is stored in Financials . - Total Revenues
-
The total revenue registered for the project.
- Progress
-
- Earned Value
-
Displays the costs/quantities that are so far allowed (Earned Value).
The performed are calculated as follows:
performed = actual progress * budget
Note:- For exceptions on this calculation see: How LN calculates the performed.
- If the project is linked to multiple contract lines with different contract types, LN considers each contract line to determine the earned value. For contract line with Fixed Price contract type, the actual overhead cost is not added to the earned value. The earned value is calculated using the formula: Budget * Progress.
- Progress
-
The progress percentage of the top activity for the project. The value in this field is based on the project activity with the least progress percentage for the project.
- Costs
-
- Commitments
-
The commitments booked for the project.
- Costs
-
The costs incurred for the project.
- Cost Forecast
-
The additional cost forecast for the end of the project that is anticipated at the end of the current period.
- Total Costs
-
The total costs incurred for the project. The total cost calculation depends on the value specified for the Leading Forecast Method in the Project Accounting Parameters (tpppc0100s000) session.
- If the value in the Leading Forecast Method is set to Estimate at Completion, the Total Cost calculation is:
Project forecast cost = Project forecast cost + Overhead forecast at completion Total costs = Project forecast cost
- If the value in the Leading Forecast Method is set to Estimate to Complete, the Total Cost calculation is:
Project forecast cost = Project forecast cost + (Overhead forecast at completion – Overhead Actual Cost) Total costs = Project actual cost + Project forecast cost
- If the value in the Leading Forecast Method is set to Estimated Extra Costs, the Total Cost calculation is:
Project forecast cost = Project forecast cost + Overhead forecast at completion Total costs = Project budget + Project forecast cost
- Cost Variance
-
The cost variance for the project.
The cost variance is calculated as follows:
variance = performed - actuals
- Variance at Completion
-
The cost VAC (Variance at Completion).
- Outstanding to Supplier
-
The amount due to the supplier to be paid against the purchase invoices. This is the amount displayed in the Invoice-to Business Partner Open Entries (tfacr2520m000) session in LN Financials .
Note: The Supplier payment is a settlement against this open entry and not against a specific invoice line. An open entry comprises many invoice lines which may or may not be linked to the same project. Hence, the amount overdue on a project cannot be determined correctly until the received amount information against the specific invoice line is stored in Financials . - Paid to Supplier
-
The amount paid to the supplier against purchase invoices. This is the amount displayed in the Invoice-to Business Partner Open Entries (tfacr2520m000) session in LN Financials .
Note: The Supplier payment is a settlement against this open entry and not against a specific invoice line. An open entry comprises many invoice lines which may or may not be linked to the same project. Hence, the amount overdue on a project cannot be determined correctly until the received amount information against the specific invoice line is stored in Financials . - Actual Number Hours
-
The number of labor hours spent on the project.
Note: The hours are displayed only if the Cost Control checkbox of the Cost Control Level Project/Cost Type is selected in the Project - Cost Control Levels (tppdm6102m000) session and is updated using the Build Actual Cost Control (tpppc4803m000) session. - Forecast Hours
-
The number of forecasted labor hours for the project.
Note: The hours are displayed only if the Cost Control checkbox of the Cost Control Level Project/Cost Type is selected in the Project - Cost Control Levels (tppdm6102m000) session and is updated using the Build Actual Cost Control (tpppc4803m000) session.
- Contract
-
- Contract
-
If this check box is selected, the contract line data is available for the project.
- Extensions
-
If this check box is selected, extensions exist for the selected project. To view and maintain the extensions, click .
- Scope
-
- Structures
-
If this check box is selected, structures exist for the specified project. To view and maintain the activity or element structures for the project, click .
- Milestones
-
If this check box is selected, milestones exist for the selected project. To view and maintain the milestones, click .
- Progress
-
- Progress
-
If this check box is selected, progress for the project is registered. The progress is registered either on elements or activities.
- Revenues
-
If this check box is selected, revenue has been registered for the selected project. To view the project revenue details, click .
- Estimate
-
- Estimate
-
If this check box is selected, estimate lines exist for the selected project. To view and maintain the estimate lines, click .
- Budget
-
- Top Down Budget
-
If this check box is selected, top-down budgets exist for the selected project. To view the current top down budget versions for the project, click .
- Budget Cost Analysis
-
If this check box is selected, budget cost analysis is defined for the selected project. To view the financial details of the project, click .
- Bottom Up Budget
-
If this check box is selected, bottom-up budgets exist for the selected project. To view budget lines with a material cost type for the project, click .
- Time Phased Budget
-
If this check box is selected, the budgeted cost of work scheduled of an activity is generated for the specific project. To view the generated planned value for the project, click .
- Quality
-
- Non-Conformance
-
Indicates if a non-conformance material report (NCMR) is linked to the selected project.
Note:This check box is applicable only if:
- The non-conformance material report (NCMR) exist for the selected project.
- The Quality Management (QM) check box is selected the Implemented Software Components (tccom0100s000) session.
- The Non-Conformance Implemented check box is selected in the Quality Management Parameters (qmptc0100m000) session.
- Requirements
-
- Purchase and Warehouse Orders
-
If this check box is selected, purchase and warehouse orders exist for the selected project. To view the transactions and the ordering flow from budget to final delivery, click .
- Service Orders
-
If this check box is selected, service orders exist for the selected project. To view the service orders, click .
- Control
-
- Cost Control
-
If this check box is selected, the actual cost control is aggregated at the project level. To monitor the project, click .
- Financial Analysis Graph
-
If this check box is selected, graph data exist for the selected project. To create a graph of the progression of costs and revenues during the project execution time, click .
- Commitments
-
If this check box is selected, commitments data exist for the selected project.
- Cost Forecast
-
If this check box is selected, cost forecast entry data exists for the selected project.
- Cost Entry
-
If this check box is selected, cost entry data exists for the selected project.
- Performance Measurement
-
If this check box is selected, performance measurement run has been conducted for the specific project. To view the performance measurement data, click .
- Project
-
The code that uniquely identifies the project.
- Status
-
The project status. The project status is important for following the right course throughout the project life cycle.
- Additional Description
-
The additional information related to the project. This can be used to communicate information about the project in different phases to the parties involved.
Note:- The Additional Description fields are synchronized with the Description fields in the General Projects (tcmcs0152s000) session.
- The values specified in the Description fields in the General Projects (tcmcs0152s000) are defaulted to the Additional Description fields in this session and vice versa.
- You can add multiple descriptions.
- Contract Amount
-
The contract amount of the project.
- Related Start Date
-
The start date of the project. Based on this date, LN considers the (budget) surcharges valid for the budget cost analysis. If the date is not specified, LN considers all the surcharges.
- Finish Date
-
The finish date of a project. The date is used for information purposes.
- General
-
- Currency
-
The project currency.
- Budget by
-
The project budget type determines the way you look at your budget.
You can budget the project by:
- Element
- Activity
- Control by
-
The project can be controlled by:
- Element
- Activity
Note:The project budget uses project control to:
- Monitor the project outcome, the revenues, the costs.
- Make a plan, if the Project control type is Activity Budget.
- Program
-
The code that identifies the program linked to the project.
- Description
-
The description or name of the code.
- Budgeting Method
-
The budgeting method of the project.
- Budget Date
-
The budget date that is used as the reference for currency transactions. By default, the budget date as specified for the project is added to the new budget lines.
- Organization Breakdown Structure
-
The organization breakdown structure defined for the project.
- Template
-
If this check box is selected, the project is of the type template and cannot be used for actual projects. The project can be used only for copying projects.
- Extension Amount
-
The sum of contract amount defined in the Project Extensions (tpptc0510m000) session