Update of Project Status (tppdm6202m000)

Use this session to change the status for a range of projects.

Field Information

Settings
New Status

Select the target status.

Work Authorization Status

If this check box is selected, the work authorization status of the projects' elements or activities is changed to Released.

Note: This option is only available if New Status is set to Active.
Financial Result Status

The financial result status can be used only if the project has a financial result. To close such a project you must use the Process Transactions (tpppc4802m000) session, then the final result is calculated.

Allowed values

Free

The project is not closed and the result is yet to be determined.

Determine Result

The financial result can be determined using the Process Transactions (tpppc4802m000) session.

Note: Infor LN allows you to set this status manually.
Result Determined

The financial result is calculated in Infor LN Financials using the Process Transactions (tpppc4802m000) session.

Note: Infor LN sets the status for this project.
Reports
Warnings

If this check box is selected, LN prints an error report.

Check Open Transactions

If this check box is selected, LN checks for any open transactions (orders, inventory , invoices), elements and activities and prints in the error report.

Note: 
  • By default, this checkbox is cleared. However, you can modify this value.
  • This checkbox is applicable only if the status of the selected project or projects are Active or Finished.
  • This checkbox is enabled only if the Warnings checkbox is selected.
Update Mode
Update Mode

Select the update mode to update the status of a project or a range of projects.

Allowed values

Update

Infor LN updates the data.

Simulate

Infor LN runs the process in the simulation mode. The results are not saved in the database. This process enables you to preview the results.

Note: If you set the New Status to Closed, and select the Update Mode, and click Update, LN generates a list of issues that must be resolved. For example, orders that are yet to be processed or if the status of a project must be set to Finished.