Project Cost Object Mapping with Service (tppdm6170m000)

Use this session to link a cost object in Project to a cost object in Service, and vice versa.

Note: 
  • Cost object mapping using this session is project specific; to create standard cost object mappings, use the Standard Cost Object Mapping with Service (tppdm0171m000) session.
  • Cost object mapping is based on project activities only; mapping to elements is not supported.
  • Materials must either be included as budget for the project itself, and then handled in Project, or treated as part of the reference activity, and then handled in Service.
  • Travel cost cannot be included in a reference activity. To link travel cost to a project, it must be budgeted.

Field Information

Project

The code that uniquely identifies the project.

Project Status

project status

Sequence Number

The mapping's sequence number.

Cost Type Service

The cost type in Service .

Item in Service

The item in Service .

Labor in Service

The task in Service . Select from the Tasks (tsmdm0115m000) session.

Cost Type

The cost type in Project that is linked to the selected cost type in Service .

Item

The item in Project .

Cost Object

The cost object in Project to which the cost object in Service is linked.

Cost Object Reference Type

Indicates whether the cost object is a standard cost object (S) or a project-specific cost object (P).