Project Equipment (tppdm6112s000)
Use this session to maintain project-specific equipment cost objects. These differ from standard equipment cost objects in that they can be used in one project only. Use the session Equipment (tppdm0512m000) to list standard equipment cost objects. Equipment cost objects represent the equipment you need to perform project tasks. You can copy default values from standard equipment cost objects. To do this, enter the code for the standard equipment cost object in the Equipment field, and then confirm that you want to copy the standard equipment data. The rest of the fields on this form are then filled in with details taken from the standard equipment cost object. This session also allows you to view the information in the list detail view. See List Detail session.
Field Information
- Project
-
The code that identifies the project.
- Project Description
-
The description or name of the code.
- Project Status
-
The status of the project.
- Equipment
-
The code that identifies the cost object. To copy details from a previously defined standard equipment cost object, enter the code here and then confirm that you want to copy the standard equipment data. The rest of the fields on this form are then filled in with details taken from the standard equipment cost object.
- Equipment
-
- General
-
- Description
-
The description or name of the code.
- Search Key
-
The search key associated with the cost object.
- Item Group
-
The item group to which the cost object belongs.
- Description
-
The description or name of the code.
- Equipment Group
-
A group of equipment codes, where the project equipment code is made part of
- Equipment Group
-
The description or name of the code.
- Responsible Department
-
The code of the department.
Note: Only departments of type Work Center and Project Management Office can be selected. - Project Order System
-
This field determines the way the equipment is ordered.
- Price Policy
-
Indicates how equipment costs are calculated.
Allowed values
- Standard Cost
-
The price of the item is calculated based on the standard cost of the item.
- Purchase Price
-
The price of the item is calculated based on the purchase price of the item.
- Derived from
-
The code of the standard equipment cost object from which this project-specific cost object is derived.
Use the session Equipment (tppdm0512m000) to list standard equipment cost objects.
- Description
-
The description or name of the code.
- Text
-
If this check box is selected, the cost object has an associated text.
- Purchase
-
- Purchase Statistics Group
-
The purchase statistics group associated with the cost object.
- Description
-
The description or name of the code.
- Purchase Price Group
-
The purchase price group places to which the equipment belongs. A purchase price group is a group of items for which price and discount agreements can be recorded.
- Description
-
The description or name of the code.
- Currency
-
The currency in which the purchase price is expressed.
- Purchase Rate
-
The default purchase price, per unit, of this cost object.
- Final Purchase Rate
-
If this check box is selected, the purchase price is the final price and cannot be changed by the Update Project Prices and Rates (tppdm6201m000) session. This means that the price remains stable for costs and budgets that reference it.
- In Home Currency
-
If your company uses an independent currency system you can view the purchase price in a different currency.
- In Home Currency
- In Home Currency
-
The description or name of the code.
- Purchase Rate Trans. Date
-
The last date on which the purchase price was changed.
- Procurement by
-
The default option to indicate the type of procurement order that is generated for the cost object.
Allowed values
- Purchase Order
- Subcontracting Procurement Order
- Equipment Procurement Order
Note:This field is displayed only if the Services Procurement is set to In Preparation or Active in the Implemented Software Components (tccom0100s000) session.
This field cannot be set to Purchase Order if:
- The Cost Determination field is set to Rate Only.
- The Subcontracting is linked to equipment procurement order.
- Services Trade
-
The code of the Services Trade used to categorize cost objects and to match the Buy-from Business Partner (supplier) during the requirements planning.
Note:- This field is displayed only if the Services Procurement field is set to In Preparation or Active in the Implemented Software Components (tccom0100s000) session.
- You must specify this value if the Procurement by field is set to Equipment Procurement Order.
- The combination of Services Trade and Buy-from Business Partner must be valid.
- This value cannot be modified if the equipment is linked to equipment procurement order.
- The specified Services Trade:
- Must exist in the Services Trade (tcmcs2113m000) session.
- Must have the Nature of Supply Type set to Equipment.
- Control
-
- Control Code
-
The control code associated with the cost object. The control code can either be a standard cost object or a project-specific cost object.
- Control Code
-
The control code associated with the cost object. S indicates that the control code is a standard cost object. P indicates that the control code is a project-specific cost object.
- Control Code
-
The control code for the cost object.
- Control Function
-
Indicates the function of this cost object for cost control purposes.
- Cost Component
-
The cost component associated with the cost object.
Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session. - Description
-
The description or name of the code.
- Cost
-
- Cost Rate Currency
-
The currency in which the cost rate is expressed.
- Cost Rate
-
The default cost rate per unit of this cost object.
- Final Cost Rate
-
If this check box is selected, the cost rate is the final rate used for cost control, and cannot be changed subsequently.
- In Home Currency
-
If your company uses an independent currency system you can view the purchase rate in a home currency.
- In Home Currency
- In Home Currency
-
The description or name of the code.
- Cost Rate Transaction Date
-
The last date that the cost rate was changed.
- Unit Data
-
- Cost Determination
-
Indicates how cost amounts relating to this cost object are calculated in the actual budget.
Allowed values
- Quantity
-
The costs related to the subcontracting cost object are calculated, by quantity-based measure of productivity.
- Amount of Time
-
The costs related to the subcontracting cost object are calculated, by time-based measure of productivity. Example, the subcontractor can be paid by the hour.
- Rate Only
-
The costs related to the subcontracting cost object are calculated, based on only an agreed rate.
- Amount Only
-
The costs related to the subcontracting cost object are calculated, based on only an amount (lump sum).
Note: The field can be set to Rate Only or Amount Only only if:- The Services Procurement is set to In Preparation or Active in the Implemented Software Components (tccom0100s000) session.
- The Procurement by field is set to Subcontracting Procurement Order.
This value cannot be modified when used for a planned PRP order or when costs are booked based on this value.
- Unit Set
-
This field indicates the default unit set to be used for this equipment cost object. The default is derived from the Project Parameters (tppdm0100s000) session.
- Description
-
The description or name of the code.
- Unit
-
The unit in which you specify quantities of the equipment: for example, when you are ordering it.
Note: The unit must be set to Piece when the Procurement by field is set to Equipment Procurement Order. - Unit Description
-
The description or name of the code.
- Product Class
-
product class
- Product Line
-
product line
- Manufacturer
-
The items' default manufacturer.
- Selection Code
- Technical Coordinator
-
The employee who is responsible for maintaining the technical item specifications and the requirements for the manufacturer of the item.
- Physical Properties
-
- Weight
-
The item's weight, expressed in the item's weight unit. This information is required on the intrastat report.
- Weight Unit
-
The weight unit in which the item's weight is expressed on the intrastat report. For details, see EU transaction reporting.
- Material
-
The material of which the item is composed. This field is only used for information.
- Size
-
The item's size. This field is only used for information.
- Standard
-
The industrial standard used to produce or purchase the item. For example, NEN3140 or ISO9000. This field is only used for information.
- Regulations
-
- Country of Origin
-
The country where the item was originally manufactured.
This field is used on Intrastat declarations.
- EAN Code
-
The bar code used to register the item.
- Environmental Compliance
-
Worldwide, various regulations exist to limit the use of hazardous chemical substances in electronic equipment preventing environmental pollution.
Companies, in most cases producers of electronic equipment, are legally required to:
- Set up and control compliancy rules.
- Verify whether purchased, engineered, manufactured, and serviced material is compliant.
- Verify whether their work processes are compliant.
This field indicates the item's environmental compliancy. The value in this field can be set by an external software application.
- Harmonized System Code
-
- Critical Safety Item
-
If this check box is selected, the equipment cost object is considered as a critical safety item.
Note: Critical Safety Item is only available when Handling Units is available. - Extra Information
-
The additional information about the item.
- Options
-
- Characteristics
-
- Operated Equipment
-
If this check box is selected, the equipment is allocated with an assigned employee to operate the same. This field is only used for information.
- Tax Code
-
The tax code associated with the cost object.
- Description
-
The description or name of the code.
- External Equipment
-
If this check box is selected, the equipment is rented from another company and is ordered with a purchase order. If this check box is cleared, the equipment belongs to your company. If for any reason the equipment is not available when you need it, you can override the no setting here and define the budget equipment line as external. You can then rent the equipment from another company.
- Self-Propelled
-
Indicates if the project equipment (truck or excavator) has self-propelling ability. By default, this check box is cleared.
- Serialized
-
If this check box is selected, the equipment is a serialized item. When a project equipment cost object is added, the item details (if specified) are defaulted from the Equipment (tppdm0112s000) session.
Note:This check box is enabled only if:
- The serial number for the specific equipment is not specified in the Serialized Items (tcibd4501m000) session.
- The equipment is not used in:
- Costs
- Requirement Planning (PRP)
- Service
- Buy-from Business Partner
-
Indicates the business partner from which you buy the equipment.
Note: When a value is specified, the combination of Services Trade and Buy-from Business Partner must be valid. - Buy-from Business Partner
-
The description or name of the code.
- Planner
-
The planner.
Note: When you specify a value in this field, LN checks if the specified employee’s data exists in the Employees - People (bpmdm0101m000) session and the employee is Active (based on the First Date of Employment and the Last Date of Employment). Else, a warning message is displayed. You can ignore the message. - Normal Cap. Utilization by Day
-
The Normal capacity of this cost object, expressed in hours per day.
- Order Lead Time
-
The order lead time for this cost object.
- Calendar
-
The code that uniquely identifies the calendar code in which you have specified availability of this equipment. This information can be taken into account during project planning.
- Description
-
The description or name of the code.
- Picture
-
- Picture
-
The picture of the project equipment. By default, the picture is also displayed in the Items (tcibd0501m000) session.
- You can also add the picture using the drag and drop operation.
- The allowed images extensions are .jpg, .gif, or .png.
- Options
-
- Register Progress
-
If this check box is selected, progress can be recorded for the cost object for the duration of the project.
- Billable
-
If this check box is selected, the selected project equipment cost object can be invoiced to the business partner.