Project - Cost Control Levels (tppdm6102m000)
Use this session to indicate the levels on which cost control must be performed for a project.
Note:
- You can access this session using the Projects (tppdm6100m000) session. The settings of the levels determines how the Build Actual Cost Control (tpppc4803m000) session must be used.
- Use the Project Parameters (tppdm0100s000) session to set the default cost control levels to be used when new projects are created.
- The cost control levels can be specified only if the status of the Project is Free.
Field Information
- Project
-
The code that identifies the project.
- Description
-
The description or name of the code.
- Project Status
-
The status of the project.
- Cost Control Level
-
Each line in the list represents a cost control level. The check boxes in the Cost Control column indicate whether or not cost control is performed for a level. You can enter several cost control levels. These levels, combined with the Cost Control field and the cost registration level determine the way LN generates control data.
Allowed values
- Activity
- Activity/Cost Component
- Activity/Cost Type
- Activity/Control Code
- Project/Cost Component
- Project/Cost Type
- Project/Control Code
- Project
- Extension
- Extension/Cost Component
- Extension/Cost Type
- Extension/Control Code
- Element
- Element/Cost Component
- Element/Cost Type
- Element/Control Code
Note:- The Project/Cost Type control level is required to generate data for the fields such as Actual Number Hours and Forecast Hours in the Project 360 (tppdm6500m100) session.
- When you set the status of the sub project to Active, the values of the cost control levels are defaulted from the main project. The data cannot be modified.
- Cost Control
-
The check boxes in this column indicate whether or not cost control is performed for the cost control levels specified in the Cost Control Level column.