Standard Surcharge by Cost Component (tppdm1171s000)
Use this session to maintain standard surcharges by cost component. The standard codes are available to all projects.The cost surcharges are posted to Financials when costs and commitments are processed through the Process Transactions (tpppc4802m000) session.
Field Information
- Company
-
The company that the surcharge applies to.
- Description
-
The description or name of the code.
- Cost Component
-
The cost component that the surcharge is calculated on.
Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session. - Sundry Cost
-
The code that identifies the sundry cost object that the surcharge is posted to.
- Sequence Number
-
This number uniquely identifies the surcharge in combination with the other surcharge characteristics, such as cost component, sundry cost, and so on. This number is automatically assigned when you create a new surcharge. Surcharges can share a common sequence number as long as they differ in at least one other characteristic.
- Percentage
-
The surcharge amount will vary depending on the budget, costs, and/or revenues (as specified in the Surcharge Type fields).
- Estimate
-
If this check box is selected, LN considers the surcharge when calculating the surcharges for the estimate for the project.
- Budget
-
If this check box is selected, the surcharge is calculated on the budgeted costs in the actual budget. The surcharge is posted as sundry cost in control data. The surcharge type indicates how the surcharge is recorded. You can check any combination of surcharge types.
- Costs
-
If this check box is selected, the surcharge is calculated based on actual costs and commitments. The surcharge is posted as sundry cost in cost registration. The surcharge type indicates how the surcharge is recorded. You can check any combination of surcharge types.
- Revenues
-
If this check box is selected, the surcharge is calculated based on revenues. This only applies to cost objects of cost type General. The surcharge is posted as sundry cost in cost registration. The surcharge type indicates how the surcharge is recorded. You can check any combination of surcharge types.
- Cost Amount
-
If this check box is selected, the estimate surcharge calculated using the Calculate Estimate Surcharges (tpest2200m100) session is added to the cost amount specified in the Estimate Lines (tpest2100m000) session.
Default value
By default, this check box is selected.
Note: This field is enabled only if the Estimate check box is selected. - Sales
-
If this check box is selected, the estimate surcharge calculated using the Calculate Estimate Surcharges (tpest2200m100) session is added to the sales amount specified in the Estimate Lines (tpest2100m000) session.
Note: This field is enabled only if the Estimate check box is selected. - Effective Date
-
The date from which the surcharge is effective. In the actual budget, the surcharge is valid if the project start date lies between the effective date and the expiry date of the surcharge. At the registration of costs and revenues, the surcharge is valid if the date of registration (voucher date) lies between the effective date and the expiry date of the surcharge.
- Expiry Date
-
The expiry date for the surcharge. In the actual budget, the surcharge is valid if the project start date lies between the effective date and the expiry date of the surcharge. For the registration of costs and revenues, the surcharge is valid if the date of registration (voucher date) lies between the effective date and the expiry date of the surcharge.
Note: If no end date has been entered, the surcharge remains valid from the effective date. - Posting Method Finance
-
Indicates how surcharges are posted to Financials following the registration of costs and revenues.
Note: This field is enabled only if the Costs check box is checked. - Fixed Enterprise Unit
-
The enterprise unit that the surcharges are posted to.
Note: This field is enabled only if the Posting Method Finance field is set to Fixed Enterprise Unit. - Element
-
The element that the surcharge is posted to. If you select an element in this field, the surcharge amount is posted to that element.
- Description
-
The description or name of the code.
- Activity
-
The activity that the surcharge is posted to. If you select an activity in this field, the surcharge amount is posted to that activity.
- Description
-
The description or name of the code.
- Cost Component (Control)
-
The cost component the surcharge is posted to.
- Description
-
The description or name of the code.