Update Estimate Line Dates from Activities (tpest2204m000)
Use this session to update the dates for expected sales and incurred cost, if the primary structure is of the Activity type. LN uses the start date and finish date of the activities. These dates are the manually entered dates or the dates updated from an External Scheduling Package (ESP). The start dates are used for the incurred cost dates. The finish dates are used for the expected sales dates.
Field Information
- Project
-
The code that identifies the project.
- Description
-
The description or name of the code.
- Status
-
The project status.
- Version
-
The code that identifies the estimate version.
- Description
-
The description or name of the code.
- Status
-
The status of the estimate version.