Contract Link to Project Structure (tpctm0160m000)

Use this session to link contract lines (CLINs) to the project structure (element/activity). You can link multiple contract lines to a project. However, you can link a specific project peg (element/activity) to only one contract line. This session also indicates if unit costs are incurred and revenues booked on the project peg. If the unit costs are incurred and the revenues are booked, it is not possible to delete such a link.

You can use the Import Activities, Import Elements, and Import Costing Breaks options only if you specify a project in the Project field of the contract line.

Note: 

  • You cannot link a Project to multiple contract lines, if the contract types are different.
  • When cost or revenues are present in cost/revenue history, you cannot modify or delete the link.
  • You can use the Import Costing Breaks option, only if the Costing Breaks check box is selected in the Implemented Software Components (tccom0100s000) session.

Field Information

Contract

The code that identifies the contract.

Description

The description or name of the code.

Contract Line

The contract line number linked to the peg.

Description

The description or name of the code.

Line

The serial number of the contract line link.

Project

The code that identifies the project.

Note: The project code is defaulted from the Contract Lines (tpctm1110m000) session. However, you can modify the value.
Description

The description or name of the code.

Element

The element linked to the contract line.

Note: You can specify a value in this field only if the Cost Control check box is selected in the Elements (tpptc1100m000) session. The activity for the element is defaulted from the Element Relationships (tpptc1505m000) session.
Description

The description or name of the code.

Activity

The activity linked to the contract line.

Note: The activity must be of the type WBS Element, Control Account, or Work Package. You can leave this field blank, however, you cannot use the element-activity combination for another contract line.
Description

The description or name of the code.

Extension

The extension linked to the contract line.

Note: 
  • If the sold-to business partner is the same for multiple contract lines, this field is used to uniquely identify the contract lines.
  • LN allows you to specify unit costs and revenues for the extension that must be linked before the unit costs and revenues are booked.
Description

The description or name of the code .

Milestone

Indicates if the Activity Type is set to Milestone in the Activities (tppss2100m000) session.

Note: You cannot modify the check box setting.
Cost Incurred

If this check box is selected, unit costs are incurred on the project peg.

Revenue Present

If this check box is selected, revenues are registered on the project peg.