Exporting data to the external scheduling package
You can use the application to export this data to the external scheduling package:
- General project information
- Trade Groups, Employees, Standard Costs Objects and the project related Project Cost Objects (also referred to as Resources)
- Activities and Budget Lines (also referred to as Tasks)
- Calendars
Example
In the External Scheduling Interface (tppss2231m000) session:
- Select the Export option.
- Select the Project, for example, PVD000004.
- Specify the Connection Node, if applicable.
- In the XML path field, specify the file path.
- In the XML file, specify the filename.
- Click Note: The progress of the export is displayed. The application also displays a message, if the import is successful. However, to generate this message you must select the Show Warnings check box. .
It is recommended that you review the information, as the details of the errors in the data setup of the application are displayed.
Note: If required, more than one external project can be linked to a LN project using the Connection Node. This enables the handling of different parts of a project by different organizational elements or planners. When you link an external project to a specific activity in the activity structure or the connection node, consequently, the external project is also connected to a LN project. For example, the construction and commissioning activities to one external project and engineering activities to another external project. It is also possible to use a different external tool or part of the planning can be handled in LN.