Labor Utilization Graph Header
The header section of the Labor Utilization Graph (tisfc8370m000) displays the Key Performance Indicators (KPIs) and the Predicted Order Completion chart for the selected time frame.
You can view this information in this section:
- Key Performance Indicators (Week): For the selected time frame, these KPIs are
displayed:
- Average Lateness: The lateness of an order is defined as the time difference between the due date and planned finish date. This time difference is calculated based on the site calendar and is expressed in days. The average lateness is the total number of late days divided by the number of orders. This value is expressed in days.
- Predicted Orders Completed in Time: The number of orders that are on time or early, divided by the total number of orders. This value is expressed in percentage.
- Number of Orders: The total number of the production orders with the status, Created, Released, or Completed.
- Number of Operations: The total number of Production Order Operations linked to the Production Department for the selected time frame.
- Average Labor Utilization: The average of utilization of all the work centers in the selected Production Department. This value is expressed in percentage.
- Predicted Order Completion: This is a graphical representation for the distribution of the early or late orders.